Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›French firm hired to jumpstart stalled Cypriot LNG project
Fossil Energy

May 26, 2025 · about 1 year ago

French firm hired to jumpstart stalled Cypriot LNG project

French-based engineering company Technip Energies has been awarded a project management consultancy (PMC) contract by Cyprus’ Natural Gas Infrastructure Company (ETYFA) for the country’s liquefied natural gas (LNG) terminal.

2 minutes read
  • LinkedIn
  • X
  • Email
FSRU Prometheus at dock
FSRU Prometheus; Source: Technip Energies via LinkedIn

French-based engineering company Technip Energies has been awarded a contract to perform project management consultancy (PMC) services at the liquefied natural gas (LNG) import terminal being developed by Cyprus’ Natural Gas Infrastructure Company (ETYFA).

As disclosed in a social media post, Technip was appointed by ETYFA to complete the LNG import terminal project in Vassilikos , Cyprus. The tender for the provision of management services for the LNG terminal was announced last September.

Valued at approximately €542 million, the project included €101 million from the Connecting Europe Facility (CEF) program as a project of common interest (PCI). It was originally scheduled to be finalized years ago, aiming to create an entry point for natural gas to Cyprus.

In November 2023, the China Petroleum Pipeline-led CMC consortium in charge of converting the Prometheus from an LNG carrier to a floating storage and regasification unit (FSRU), shared that sea trials were completed . At the time, the terminal was expected to be opened in July 2024.

One month after the delivery ceremony for the FSRU taking place in January 2024, CMC alleged that ETYFA “withheld tens of millions in payments, changed the nature and scope of the project and has consistently interfered with essential design and procurement activities.”

The project faced another obstacle last summer, when the European Public Prosecutor’s Office (EPPO) in Nicosia, Cyprus, launched an investigation into the LNG terminal project due to suspected procurement fraud, misappropriation of European Union (EU) funds, and corruption.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyLiquefied Natural GasOil & GasBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1After Fugro, TDI-Brooks selected for surveys offshore Timor-Leste
  2. 2Vessel duo's APAC drilling support jobs boost Solstad's backlog by up to $30 million
  3. 3New BP deal deepens Aker Solutions’ North Sea footprint
  4. 4Wales’ national marine energy test center secures Crown Estate investment

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free