Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›JERA plans Chita LNG-fueled power plant rejuvenation
Clean Fuel

October 7, 2020 · about 6 years ago

JERA plans Chita LNG-fueled power plant rejuvenation

Japanese utility JERA has submitted its environmental document for the Chita power plant development to the authorities.

1 minutes read
  • LinkedIn
  • X
  • Email
JERA plans Chita LNG-fueled power plant rejuvenation
Courtesy of JERA

Japanese utility JERA has submitted its environmental document for the LNG-fueled Chita power plant development to the authorities.

As a response to the business conditions such as future electricity supply and demand, JERA is considering the construction of two new LNG-fueled units at the facility.

The Chita thermal power station construction plan described in the document involves decommissioning existing units 1 through 5 (while retaining unit 6) and constructing new units 7 and 8.

In order to reduce carbon dioxide emissions, for new units 7 and 8 the plan adopts the latest high-efficiency combined cycle power generation system.

In addition, when the plan has been carried out, the environmental burden due to smoke and warm wastewater is expected to be lower than for operations at the existing facility.

The five units set for decommissioning have a total installed capacity of 3,112 MW. Units 1 through 4 are set to be decommissioned in FY 2021, the plan shows. Unit five is set for decommissioning in FY 2026.

The units 7 and 8 will have a 650 ME generation capacity each with the start of operation planned for August 2027 and December 2027, respectively. With the 854 MW generated by unit 6, the Chiba thermal power plant will have a total generation capacity of 2,154 MW.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelLNGBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free