Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Glenfarne requests more time to build Magnolia LNG
Clean Fuel

September 15, 2020 · about 6 years ago

Glenfarne requests more time to build Magnolia LNG

Units of Glenfarne Group and Kinder Morgan have filed a request with the regulator seeking an extension for the Magnolia LNG project development.

2 minutes read
  • LinkedIn
  • X
  • Email
Glenfarne requests more time to build Magnolia LNG
Courtesy of LNG Limited

Units of Glenfarne Group and Kinder Morgan have filed a request with the regulator seeking an extension for the Magnolia LNG project development.

In its filing to the Federal Energy Regulatory Commission, Magnolia LNG and Kinder Morgan Louisiana Pipeline jointly requested an additional five year to place respective facilities into service.

To remind, Magnolia LNG, acquired by Glenfarne earlier this year , is an 8.8 million tonnes per annum (mtpa) LNG export project that has completed the FERC permitting process.

The Kinder Morgan Louisiana Pipeline will deliver 1.4 billion cubic feet per day of natural gas to the LNG project.

Both projects were directed to make the respective facilities available for service by April 15, 2021, initially. The companies are now requesting the date to be April 15, 2026.

However, global market conditions have impacted the developer’s ability to secure long-term offtake contracts and achieve a final investment decision, the request reads.

The offtake deals with international customers are critical to securing project financing and achieving FID. A short-term over-supply across the global LNG market, coupled with disruptions in the China-United States LNG trade and the ongoing COVID-19 pandemic, have delayed these offtake contracts and further delayed FID for the project.

KMLP’s construction is dependent on Magnolia LNG achieving FID.

In addition, on July 31, 2020, Magnolia LNG and KMLP executed an amendment to extend the parties’ binding precedent agreement for firm natural gas transportation service up to 1.4 Bcf/d, sufficient to satisfy the full 8.8 mtpa capacity of the Magnolia LNG project.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelLNGBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push