USACE: All Set for Marshfield’s East Jetty Project

Business & Finance

Maintenance and repairs to the East Jetty feature of the Federal Navigation Project (FNP) in Green Harbor in Marshfield, Mass., will be completed under the terms of a $839,500.00 contract issued recently by the USACE’s New England District.

Image source: ack-marinecontracting.com

Work will be accomplished by ACK Marine & General Contracting, LLC, of Quincy, Mass. Work is scheduled to start in the following days and will take several months to complete.

The contract was awarded on May 17, 2018, USACE said.

Green Harbor in Marshfield is situated in the northwestern end of Cape Cod Bay, about 30 miles southeast of Boston and nine miles north of Plymouth Harbor.

“The work consists of repairing a 150-foot section of the east jetty at Green Harbor,” said Project Manager Bill Kavanaugh, of the Corps’ New England District, Programs/Project Management Division in Concord, Mass. The east jetty was damaged during winter storm Juno in 2015 and subsequent storms.

Approximately 1,200 tons of new armor stone will be required to make repairs to the landward section of the jetty. New armor stone will vary in size from 4-7 tons, said USACE.

Work includes excavating, removing, stockpiling, installing and reworking existing armor stone as well as acquiring and installing new armor stones in the jetty repair area.

The Notice to Proceed was issued on May 25, 2018 and the contractor mobilized to the site on July 13, 2018. The first 300 tons of stone were delivered to the site on July 16, 2018 and physical construction of the jetty is anticipated to start the week of July 23, 2018.

Completion is anticipated in late September 2018.