Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›BP-led Tortue FLNG project’s Phase 1 58 pct done
Clean Fuel

May 10, 2021 · about 5 years ago

BP-led Tortue FLNG project’s Phase 1 58 pct done

The BP-led Greater Tortue Ahmeyim LNG project on the maritime border of Mauritania and Senegal is progressing.

2 minutes read
  • LinkedIn
  • X
  • Email
BP-led Tortue FLNG project's Phase 1 58 pct done
Courtesy of BP

The BP-led Greater Tortue Ahmeyim LNG project on the maritime border of Mauritania and Senegal is progressing.

Dallas-based Kosmos Energy informed the project’s Phase 1 was 58 per cent done at the end of the first quarter.

On Monday Kosmos Energy reported material progress across all of the major workstreams, including the FPSO, Floating LNG vessel, hub terminal (concrete breakwater) and subsea infrastructure.

The partnership is targeting Phase one to be around 80% complete by year end.

Kosmos expects completion of the FPSO sale and lease-back in the second quarter of 2021 as previously communicated. The process remains on track with documentation being finalized and the government approval process well underway.

The Greater Tortue Ahmeyim project will produce gas from an ultra-deepwater subsea system and mid-water floating production, storage and offloading (FPSO) vessel, which will process the gas, removing heavier hydrocarbon components.

The gas will then be transferred to a floating liquefied natural gas (FLNG) facility at a nearshore hub located on the Mauritania and Senegal maritime border.

BP has secured the services of Golar’s Gimmi FLNG on a 20-year deal. The pair agreed a delay in delivery of the vessel due to the effects of the Coronavirus pandemic. BP now expects the delivery of the in 2023, the same year when the project is expected to produce the first gas.

The FLNG facility is designed to provide circa 2.5 million tonnes of LNG per annum on average, with the total gas resources in the field estimated to be around 15 trillion cubic feet.

The project, the first major gas project to reach FID in the basin, is planned to provide LNG for global export as well as making gas available for domestic use in both Mauritania and Senegal.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelFossil EnergyLNGOil & GasBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free