Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›CIP selects partners to build Taiwanese O&M base
Offshore Wind

August 6, 2020 · about 6 years ago

CIP selects partners to build Taiwanese O&M base

Copenhagen Infrastructure Partners (CIP) has teamed up with two Taiwanese companies to build an offshore wind farm operations and maintenance base in Changhua County, Taiwan. CIP has partnered with CECI Engineering Consultants, Inc. and Reiju Construction to build the O&M base. The project is curren

1 minutes read
  • LinkedIn
  • X
  • Email
CIP selects partners to build Taiwanese O&M base
CECI Engineering Consultants

Copenhagen Infrastructure Partners (CIP) has teamed up with two Taiwanese companies to build an offshore wind farm operations and maintenance base in Changhua County, Taiwan.

CIP has partnered with CECI Engineering Consultants, Inc. and Reiju Construction to build the O&M base.

The project is currently in its design stage and is expected to be issued the construction permit in the fourth quarter of 2020.

The base is scheduled to be completed by the end of 2021.

The Operation & Maintenance Center is planned to be a two-storey steel structure with a floor area of about 1,000 m2 and will include offices, maintenance, handling, storage, and other areas.

CIP reached a final investment decision on the 589 MW Changfang and Xidao offshore wind project in February 2020.

The wind farm is located in the Taiwan Strait, some 13-15 kilometres off the Taiwanese west coast at the Fangyuan Township, Changhua County.

It will feature 62 MHI Vestas 9.5 MW wind turbines scheduled to be commissioned in the first quarter of 2024.

Onshore construction on the project started in July 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free