Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Kajima to handle construction at 700 MW Japanese offshore wind farm
Offshore Wind

June 12, 2020 · about 6 years ago

Kajima to handle construction at 700 MW Japanese offshore wind farm

Japanese consortium developing the Akita Yurihonjo offshore wind farm has selected Kajima Corporation as the project’s contractor in charge of construction. The consortium, led by Renova, is developing the Akita Yurihonjo project through the special purpose company – Akita Yurihonjo Offshore Wind GK

2 minutes read
  • LinkedIn
  • X
  • Email
Kajima to handle construction at 700 MW Japanese offshore wind farm
MHI Vestas/Illustration

Japanese consortium developing the Akita Yurihonjo offshore wind farm has selected Kajima Corporation as the project’s contractor in charge of construction.

The consortium, led by Renova, is developing the Akita Yurihonjo project through the special purpose company – Akita Yurihonjo Offshore Wind GK (AYOW).

Members of the consortium also include Cosmo Eco Power, JR-EAST Energy Development, and Tohoku Electric Power.

The wind farm will feature MHI Vestas wind turbines and have a generating capacity of around 700 MW.

The project is expected to enter the construction phase in FY 2021 and become operational from FY 2024 onward.

AYOW is currently conducting environmental impact assessments and various other surveys, and examining the project’s technical specifications.

The project has been under development since 2015 and a project plan was drawn up based on the Second Phase of Akita Prefectural Strategy for New Energy Industries formulated by Akita Prefecture in 2016.

AYOW began wind condition measurements of the site in 2016 and commenced seabed ground surveys in the following year. In 2017, AYOW also began carrying out the procedures for environmental impact assessments and holding briefings to explain the project to local stakeholders.

Kajima was the general contractor on the project led by NEDO and TEPCO to install the first fixed-foundation offshore wind turbine in Japanese waters back in 2013.

The company is also the EPCI contractor for the 140 MW Akita Noshiro project, the first commercial-scale offshore wind farm in Japan.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free