Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Construction Works in Full Swing in Carteret County
Dredging

February 11, 2020 · about 6 years ago

Construction Works in Full Swing in Carteret County

Works on the Phase II of the Carteret County Post Florence Renourishment Project are in full swing now, informs the county’s Shore Protection Office. “As expected, we’re experiencing some strong productivity a little over two days into the project as the sand is being pumped eastward from the first

1 minutes read
  • LinkedIn
  • X
  • Email
Construction Works in Full Swing in Carteret County
Image source: Carteret County

Works on the Phase II of the Carteret County Post Florence Renourishment Project are in full swing now, informs the county’s Shore Protection Office.

“ As expected, we’re experiencing some strong productivity a little over two days into the project as the sand is being pumped eastward from the first subline landing ,” the county said.

The officials also added that the second “subline” is scheduled to be set today.

Great Lakes Dredge & Dock (GLDD) brought in their hopper dredger Liberty Island to perform this nourishment project.

Under the plan, GLDD will later in March bring their largest hopper dredge, the Ellis Island to the site to relieve the Liberty Island of her duties and continue “leapfrogging” down the beach to finish the Phase II effort in West Emerald Isle before the April 30th environmental window closes.

Overall, phase II of the Post Florence Project will utilize 1,995,000 cubic yards (cy) of sand obtained from the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project.

West Emerald Isle (EI), Salter Path (IB), Pine Knoll Shores (PKS), and West Atlantic Beach will receive 345,000 cy, 140,000 cy, 990,000 cy, and 520,000 cy, respectively along 9.5 miles of shorelines.

Phase III of the Post-Florence Renourishment Project is tentatively scheduled for winter 2020-2021 and will encompass Central and Western Emerald Isle.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free