Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Schmidbauer Doing Heavy Lifting for Walney Extension
Wind Farms

March 8, 2017 · about 9 years ago

Schmidbauer Doing Heavy Lifting for Walney Extension

Van Oord Offshore Wind Projects has contracted the heavy-lift specialist, Schmidbauer Group, to handle the heavy load logistics for the foundation components of the 660MW Walney Extension offshore wind farm in the UK.

1 minutes read
  • LinkedIn
  • X
  • Email

Van Oord Offshore Wind Projects has contracted the heavy-lift specialist, Schmidbauer Group, to handle the heavy load logistics for the foundation components of the 660MW Walney Extension offshore wind farm in the UK.

The work started in November 2016 and will continue until mid-2017.

Schmidbauer is tasked with unloading, storing and transporting the transition pieces (TPs) weighing up to 600 tonnes and monopiles (MPs) weighing up to 1,030t at the feeder harbor in Belfast.

Here, components of a total of 87 wind turbines are stored and will be taken by tugboats or an installation vessel to the offshore wind farm.

DONG Energy, the owner and operator of the wind farm, started offshore construction works at the site some 19 kilometres off the coast of Cumbria in the second half of February.

The wind farm will consist of 40 8MW MHI Vestas and 47 7MW Siemens wind turbines.

Van Oord was contracted to transport and install the 87 foundations at the site, and the jack-up vessel Seajacks Scylla was hired to transport and install the turbines.

The inter-array cables will be installed by VBMS, and the subsea export cables will be laid by DeepOcean’s Maersk Connector.

Walney Extension, located next to the 367.2MW Walney 1 & 2 offshore wind farms, will be the largest wind farm in the world when built and is expected to be generating clean electricity by 2019.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1When conditions become marginal, who makes the call?
  2. 2RINA and Thailand's PTT sign two innovation and decarbonization-focused MoUs
  3. 3GasEntec’s billion-cubic-feet FSRU concept earns go-ahead from Lloyd’s Register
  4. 4Prysmian extends 30-year copper partnership with new supply agreement

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free