Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›FID In Place for Nissum Bredning Project, Siemens’ Tech Testbed
Wind Farms

September 20, 2016 · about 10 years ago

FID In Place for Nissum Bredning Project, Siemens’ Tech Testbed

Nissum Bredning Vindmøllelaug and Jysk Energi, which placed the winning bid for Nissum Bredning Vind project earlier this year, following a call for tender from Danish Energy Agency’s (DEA), have made the final investment decision for the 28MW pilot project in northern Denmark. The commercial aspect

2 minutes read
  • LinkedIn
  • X
  • Email

Nissum Bredning Vindmøllelaug and Jysk Energi, which placed the winning bid for Nissum Bredning Vind project earlier this year, following a call for tender from Danish Energy Agency’s (DEA), have made the final investment decision for the 28MW pilot project in northern Denmark.

The commercial aspect of the offshore wind technology to be tested in the project is expected to show a significant positive impact on the Levelized Cost of Electricity (LCoE), according to Siemens, which is testing its new offshore wind solutions within the project.

The project will see Siemens delivering four 7MW direct drive wind turbines and their gravity jacket foundations, as well as a new 66kV voltage solution including a new transformer, cable and switchgear systems, along with further innovations regarding tower and controller settings.

“We are proud to be part of Nissum Bredning Vind offshore wind power plant. Since the Danish Ministry of Energy tendered the project as an official test bed for new technologies and integrated design, we’ve looked forward to this exciting project,” said Michael Hannibal , CEO Offshore at Siemens Wind Power and Renewables Division. “This gives us the opportunity to simultaneously test and promote our innovations to achieve further cost reductions in offshore wind.”

Nissum Bredning Vind offshore wind power plant will get support by receiving a guaranteed feed-in tariff of DKK 0.7/kWh (EUR 0.09/kWh) for the initial 10 years for the first 50,000 full load hours of operation.

Turbine installation is scheduled for summer 2017, with commissioning expected to take place in the third quarter of next year.

Four proposals were submitted at DEA’s invitation for tenders for the test scheme: one by EDF Energies Nouvelles, two by European Energy, and one by Nissum Bredning Vindmøllelaug.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free