Twelve wind turbines up at Moray East OWF

Project & Tenders

Twelve Vestas (MHI Vestas) 9.5 MW wind turbines have been installed so far at the Moray East project site, located some 22 kilometres off the Aberdeenshire coast.

Moray East

The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s Bold Tern jack-up vessel, which is picking up the components at the Port of Nigg, where Global Energy Group’s facility is serving as the onshore pre-assembly site for the project.

The first four Vestas 9.5 MW units, which Bold Tern carried in the first batch to be installed, were in place by the end of January.

Related Articles

The commissioning work is being performed from Acta Centaurus and supported by two crew transfer vessels, HST Harri and Windcat 40.

The 100-turbine, 950 MW Moray East wind farm is being developed by Moray Offshore Windfarm East Ltd (MOWEL), a joint venture company owned by Ocean Winds (56.6%) Diamond Green Limited (33.4%), and CTG (10%).

The project is scheduled to be fully commissioned in 2022.