  • 3 May 2013
    Business & Finance, Operations & Maintenance

    During the period 11 – 13 March 2013, the Petroleum Safety Authority Norway (PSA) carried out an audit of Eni Norge AS’ (Eni’s) compliance with requirements for establishment and implementation of technical and operational barriers in the Goliat project. Objective The objective of the audit was to verify how Eni, through operations preparations, ensures compliance […]

  • 12 November 2014
    Equipment

    From 23 to 25 September 2014, the Petroleum Safety Authority (PSA) Norway carried out an audit of Det norske oljeselskap ASA (Det norske) and barrier management in the Ivar Aasen development project, in the North Sea.  The Ivar Aasen field is situated west of the Johan Sverdrup field in the North Sea, around 30 kilometres south of […]

  • 9 May 2014
    Business & Finance, Operations & Maintenance

    The Petroleum Safety Authority Norway (PSA) has carried out an audit of Statoil and emergency preparedness management of the Norne FPSO From 31 March to 2 April 2014. Objective The objective of the activity was to gain an overview of processes and systems that contribute to ensuring comprehensive emergency preparedness management on the Norne FPSO. Result […]

  • 3 August 2016

    Norway’s offshore safety body, the Petroleum Safety Authority (PSA), has found several non-conformities and improvement points during the audit of Total’s Martin Linge development, offshore Norway. Total E&P Norge (Total) is the operator of the Martin Linge field, located near the British part of the North Sea about 42 kilometers west of the Oseberg field. […]

  • 9 May 2014
    Business & Finance, Equipment, Operations & Maintenance, Research & Development

    The Petroleum Safety Authority Norway (PSA) carried out an audit of detailed engineering of the Polarled pipeline from 11 to 12 March 2014. Objective The objective of the audit was to monitor that the project has been planned and carried out in compliance with applicable regulations and recognised norms, and that requirements in the HSE […]

  • 14 December 2022
    Authorities & Government, Business & Finance, Business Developments & Projects, Operations & Maintenance, Project & Tenders, Regulation & Policy, Rules & Regulation, Safety

    Norwegian offshore safety regulator has carried out an audit of Odfjell Drilling and its risk management on one of its semi-submersible rigs.

  • 22 April 2022
    Authorities & Government, Business & Finance, Business Developments & Projects, Exploration & Production, Project & Tenders, Regulation & Policy, Rules & Regulation

    Equinor has received two types of consent from Norway’s offshore safety regulator for ops in the North Sea with Odfjell Drilling-owned rigs.

  • 28 May 2018
    Exploration & Production

    Offshore driller COSL has some work to do to make its COSLInnovator semi-submersible drilling rig fully compliant with the Norwegian regulation.

  • 9 December 2016

    Norwegian offshore safety body, the Petroleum Safety Authority (PSA), has turned a notification of order to Prosafe into a formal order as a result of the company not fixing irregularities found during an audit of the Safe Scandinavia tender support vessel (TSV) in September 2015. The Safe Scandinavia is an accommodation rig converted to a TSV in […]

  • 13 November 2019
    Business & Finance, Operations & Maintenance

    Petroleum Safety Authority (PSA) Norway has carried out an audit of Vår Energi and its pipe and subsea portfolio on the Norwegian Continental Shelf. The audit, from October this year, included inspection of Vår Energi and its portfolio of pipelines, risers, control cables and subsea facilities on the NCS. The objective of the audit was […]

  • 20 June 2018
    Business & Finance, Operations & Maintenance

    Petroleum Safety Authority (PSA) Norway has recently carried out an audit of integrity and barrier management for flexible risers and systems for pressure safety/emergency shutdown at Snorre A. PSA said it identified three non-conformities in connection with: Operating parameters for flexible risers and jumpers; Follow-up of emergency shutdown valves; and Integrity management of flexible risers […]

  • 15 December 2011
    Business & Finance

    The Petroleum Safety Authority Norway (PSA) carried out an audit targeting drilling and well technology systems on board the West Elara jack-up drilling rig. North Atlantic Drilling has applied to the PSA for an AoC (Acknowledgement of Compliance) for West Elara. The facility has not previously had an AoC as it is a newbuild which […]

  • 21 December 2017

    The Norwegian offshore safety body, the Petroleum Safety Authority (PSA), has found an improvement point during an audit of waves on deck on Statoil’s eight facilities off Norway.

  • 14 July 2014
    Business & Finance

    On 20 and 21 May 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil’s barrier management in the early phase of the Johan Sverdrup project prior to the plan for development and operation (PDO). Objective The objective of a pre-PDO audit is to monitor that the operator’s plans and decisions in […]

  • 30 December 2011
    Business & Finance, Equipment

    On 7 and 8 December 2011, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil in connection with the engineering of load-bearing structures on Valemon’s jacket. Objective The objective was, through spot checks, to ensure the engineering of the load-bearing structures is taking place pursuant to the applicable regulatory framework. Results No […]

  • 23 April 2018
    Exploration & Production

    Norway’s PSA has found several non-conformities and improvement points during an audit of the Askepott rig and Oseberg H platform off Norway.

  • 16 December 2022
    Authorities & Government, Business & Finance, Business Developments & Projects, Exploration & Production, Operations & Maintenance, Project & Tenders, Regulation & Policy, Rules & Regulation, Safety, Vessels

    Norwegian regulator has carried out an audit of Vår Energi and its management of barriers and maintenance on an FPSO modification project.

  • 15 December 2022
    Authorities & Government, Business & Finance, Business Developments & Projects, Project & Tenders, Regulation & Policy, Rules & Regulation, Safety

    Norwegian regulator has carried out an audit of Equinor and its completion of electrical facilities on the Johan Castberg FPSO.

  • 6 December 2016

    The Petroleum Safety Authority (PSA) Norway has carried out an audit of Wintershall’s barrier management at Brage. Wintershall Norge is the operator of the Brage field, located in the North Sea, approximately 13 kilometers east of Oseberg. Brage has been developed using an integrated facility on a steel jacket. The oil from the field is transported […]

  • 15 July 2014
    Business & Finance

    On 29 April 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Premier Oil’s management of the early phase of the Bream project prior to the plan for development and operation (PDO). Objective The objective of a pre-PDO audit is to monitor that the operator’s plans and decisions in the early phase […]

  • 14 November 2018

    The Petroleum Safety Authority (PSA) has found irregularities during an audit of ConocoPhillips’ Ekofisk 2/4 J platform.

  • 16 November 2018

    The PSA has given Lundin Norway the consent to change the area contingency planning on the Edvard Grieg field.

  • 4 July 2012
    Business & Finance

    On 10 and 11 May 2012, the Petroleum Safety Authority Norway (PSA) carried out an audit of the engineering of load-bearing structures on Eldfisk 2/7-S’ steel jacket, located in the Norwegian part of the North Sea. The objective of the audit activity was to verify that the engineering of load-bearing structures was in compliance with […]

  • 15 July 2014
    Business & Finance, Project & Tenders

    On 29 April 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Premier Oil’s management of the early phase of the Bream project prior to the plan for development and operation (PDO). The objective of a pre-PDO audit is to monitor that the operator’s plans and decisions in the early phase of […]

  • 5 November 2012
    Equipment

    During the period 25 – 26 September 2012, the Petroleum Safety Authority Norway (PSA) conducted an audit of ConocoPhillips Skandinavia AS’ (CoPSAS) follow-up of electrical installations and personnel responsible for such installations. The objective of the audit was to verify compliance with regulatory provisions and the audit particularly targeted those parts of the company’s management […]