DEME Begins SeaMade Foundations Installation

Operations & Maintenance

DEME’s installation vessel ‘Innovation’ has started foundations installation at the SeaMade offshore wind farm in Belgian North Sea.

With a 487 MW capacity SeaMade is the largest offshore wind farm in Belgium. SeaMade stands for a combination of two offshore wind projects, previously known as Mermaid (235 MW) and Seastar (252 MW).

DEME’s scope includes the installation of the 58 foundations and all inter-array cables, the installation of two offshore substations and the 220 kV submarine high voltage cable installation.

In spring 2020, the 8,4 MW turbines will be installed on the foundations. Before the end of 2020, SeaMade will provide renewable energy to 500,000 households in Belgium.

“After months of careful planning and engineering, it is great to kick-off the offshore works at the largest offshore wind farm in Belgium,” said Luc Vandenbulcke, CEO of DEME. “For now, this is the last wind farm developed in the Belgian North Sea. Thanks to our country being at the forefront of offshore renewable energy, we had the opportunity to develop a leading cluster of Belgian companies involved in the construction of offshore wind farms globally. We look forward to working with our partners and all stakeholders on the SeaMade project, and are confident also in the future our combined expertise can play a major role in Belgium’s ambition to double the offshore wind capacity to 4 GW by 2025.”

“We are proud that SeaMade brings the Belgian offshore wind capacity to 2,262 MW by 2020, exactly as has been anticipated by the Belgian federal government,” added Mathias Verkest, CEO at SeaMade. “This capacity will produce more than 8 TWh annually, which is approximately 10% of total electricity demand and 50% of the total household consumption. Even with the limited surface of the Belgian North Sea, Belgium is the fifth producer of offshore wind worldwide. Beyond 2020, the offshore wind energy capacity in the Belgian North Sea can be further developed and doubled to at least 4,000 MW. We trust solutions will be found allowing an adequate and timely grid connection for this second round.”