Australia Pacific LNG plant to undergo maintenance in March, April

Ports & Logistics
Image courtesy of Australia Pacific LNG

The Australia Pacific liquefied natural gas (LNG) export plant located on Curtis Island in Queensland will shut down for planned maintenance in March and April.

The two-train 9 mtpa liquefaction plant will close one train on March 8-23 and the other on April 14-29, according to a notice submitted to the Australian Energy Market Operator (AEMO).

Australia Pacific LNG is a joint venture between ConocoPhillips (37.5%), Origin (37.5%) and Sinopec (25%).

Origin is responsible for the operation of the APLNG gas fields and main gas transmission pipeline while ConocoPhillips operates the LNG facility.

 

LNG World News Staff