Northern Lights subsea template before installation; Source: Equinor CCS

Rystad: Europe could invest $35 billion in CCS by 2035

Transition

After many years of expensive carbon capture and storage (CCS) studies and test centres, Europe has reached a point where big-scale developments are financially sensible, a Rystad Energy analysis shows.

Northern Lights subsea template before installation; Source: Equinor

Rystad said on Monday that CSS could trigger up to $35 billion in development spending until 2035 – by which time as much as 75 million tonnes of CO2 could be captured and stored per year on the continent by 2035.

According to the energy intelligence firm, there are around 10 larger projects in Europe alone with both carbon capture and storage that are planned and have a high chance of being operational by 2035.

Most of them are located around the North Sea in Norway, the UK, Denmark, and the Netherlands, but there are also projects on the drawing board in Ireland and Italy.

Although most of the projects are expected to be on-line from the middle of this decade, investments and contracts awarded to suppliers will already start to grow significantly from 2021–2023, as most projects have a development timeline of three to five years.

Total capital investment for these projects is expected to reach $30 billion, in addition to operational expenditure totalling $5 billion until 2035.

Rystad said that about half of the capex would be consumed by the facilities at the source, with CO2-capture equipment and facility construction making up the largest part. Storage investments will make up 15 per cent and will mainly comprise well-related services to store the CO2 safely in underground reservoirs.

Transport and operations take 35 per cent and relate to trunk lines, shipping and infrastructure maintenance costs.

Rystad Energy CCS

The first three projects that are due to become operational are Acorn CCS, Northern Lights, and Porthos, which Rystad claims will be “game-changing” as they will “de-risk the overall CCS uncertainty”. More than twice as many projects, in count and size, are likely to follow.

With the projects so far planned in Europe, we expect that 3 million tpa of CO2 capture and storage capacity will be added each year from 2021 to 2025, then jumping to 7 million tpa in the next five-year period 2026–2030. By 2035 we are looking at a total installed capacity of around 75 million tpa, where almost 80% will come from UK projects.

Currently, there are only two complete full-scale CO2 projects operational in Europe – the CO2 injection projects at Norway’s offshore fields Sleipner and Snohvit, with a combined CO2 capture and storage capacity of around 1.5 million tpa.

Looking at the bigger picture, Europe has about 1,000 larger industrial sites, such as cement plants, steel producers, fossil power, and waste-to-energy plants, that could all be candidates for capturing CO2.

About 250 of these have reasonable shipping distance to send CO2 to be stored in the North Sea.

An opportunity for OCTG and linepipe suppliers

James Ley, Rystad Energy’s SVP of energy service research, stated: “Developing CCS projects is also an opportunity for the linepipe and oil-country tubular goods (OCTG) industry, with a new market about to open up for suppliers looking to expand beyond oil and gas“.

Equinor, Shell, and Total’s Northern Lights CO2 storage project in Norway will, for example, require around 12,000 tonnes of carbon seamless linepipes for the export line, Rystad Energy estimates, and tenders for these tonnages could be expected soon.

Related Article

For subsea installation, Saipem, Technip FMC, and Subsea 7 are all competing for this job and Rystad believes that Saipem and Subsea 7 are leading the race.

From an OCTG perspective, the initial requirements for Northern Lights are likely to be low as the project just calls for one well to be drilled in the first phase, following a test well drilled in March 2020. This injection well is expected to require high-chromium grades of OCTG tubing. Northern Lights Phase 1 is expected to cost $760 million, with 56 per cent of the contracts going to Norwegian suppliers.

As standard renewable technologies that have some maturity in Europe such as solar installations and offshore wind farms are increasingly gaining market share, CCS projects will face competition and have to prove cost-worthy“, Martinsen added.