Equinor Plans Johan Sverdrup Start Up Ahead of Schedule

Operations & Maintenance

Equinor and its partners have started preparation for production start from the Johan Sverdrup field in October this year, one month ahead of schedule.

The Johan Sverdrup field in the North Sea. Photo: Espen Rønnevik/Øyvind Gravås/Equinor

The Johan Sverdrup development continues to progress well through the final stages of preparation for operations, Equinor explained. As a result, Equinor and its partners, Lundin Norway, Petoro, Aker BP and Total, are accelerating the planned schedule for production start-up.

Since the Plan for development and operation (PDO) for Phase 1 of the Johan Sverdrup project was submitted in 2015, the project has seen both a significant cost reduction as well as an acceleration in the start-up schedule from late December 2019 to now October.

Around this time last year, we accelerated the expected schedule for production start-up of Johan Sverdrup to November 2019. Now, as we enter the final stretch of the project, we believe it is possible to start production up to one month earlier,” said Anders Opedal, executive vice president for Technology, projects & drilling in Equinor.

“Being in the position to potentially accelerate first oil for a mega-project like this, demonstrates the high quality of execution in the Johan Sverdrup development. This is to a large extent due to the close collaboration with our partners and suppliers since day one in the project.”

The current focus of the Johan Sverdrup project is on completing the testing of the equipment and systems needed for the full field centre – spanning four platforms and three interconnected bridges and associated modules – to function and perform as one installation.

Assuming all testing can be completed without encountering any issues with critical equipment, start-up of production should be ready during the month of October.

Based on the remaining known scope of work, we are increasingly confident of starting production at Johan Sverdrup soon. At the same time, given the very size of the Johan Sverdrup development, there will always be a risk that we in the final testing phase come across unforeseen issues that end up extending the start-up period. Ultimately, we’ll only start producing when it is safe and prudent to do so,” added Opedal.