Leighton Wins LOFS Contract from Qatar Gas

Business & Finance

Leighton Wins LOFS Contract from Qatar Gas

Leighton Offshore has been awarded another project by Qatar Gas after successfully delivering the replacement of their SPM 1 floating hoses earlier in the year.

Leighton’s scope of work For Qatargas Phase 2 will include:

– Floating Hose change out works on SPM 2, including flushing of SPM system, installing, pressure testing of new hose strings.

– Replacement of SPM 2 subsea hoses, including new piggy back Fiber Optic & Hydraulic Umbilical’s , dewatering, Pressure Testing and commissioning assistance for the Complete SPM No 2 System.

– A Second Scope is to change out the Complete Subsea Hose System on the Qatargas SPM No 1 Buoy, including new piggy back Fiber Optic & Hydraulic Umbilical’s , dewatering, Pressure Testing and commissioning assistance for the Complete SPM No 1 System.

The project team is currently mobilized in field delivering the project which will be completed by November.

Project Manager Justin Pietersen said: “We are very pleased to be undertaking further work for a client such as Qatar Gas. The Leighton Offshore Life of Field services team has more than 100 year’s cumulative experience in SPM related works scopes with a strong focus on safe and environmentally sound operating practices. We have the people, systems and equipment to provide innovative solutions for our clients operations and maintenance needs.”

[mappress]

Press Release, November 08, 2013