Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business Developments & Projects›Offshore substation, export cable works completed at Taiwan’s Fengmiao 1 OWF
Business Developments & Projects

August 6, 2026 · about 1 month ago

Offshore substation, export cable works completed at Taiwan’s Fengmiao 1 OWF

Two offshore construction milestones have been completed at the 495 MW Fengmiao 1 offshore wind farm in Taiwan, with Jan De Nul finalizing the export cable connection to the offshore substation and CDWE completing the installation of the offshore substation and its foundation. Jan De Nul said on Aug

2 minutes read
  • LinkedIn
  • X
  • Email
Offshore substation, export cable works completed at Taiwan’s Fengmiao 1 OWF
Jan De Nul via LinkedIn

Two offshore construction milestones have been completed at the 495 MW Fengmiao 1 offshore wind farm in Taiwan, with Jan De Nul finalizing the export cable connection to the offshore substation and CDWE completing the installation of the offshore substation and its foundation.

Jan De Nul said on August 5 that its cable-laying vessel (CLV) Willem de Vlamingh had pulled the project’s two high-voltage export cables into the offshore substation, completing the offshore grid connection after previously loading, installing, burying and protecting the cables.

Earlier this year, the company completed the installation of the 45-kilometer and 44-kilometer export cables before wet storing them offshore pending installation of the offshore substation.

Related Articles

Cabling

Jan De Nul installs export cables for Taiwan’s Fengmiao 1 offshore wind farm

1 min read

Also on August 5, CDWE, the joint venture between DEME and Taiwan’s CSBC, announced that the company had completed the transport and installation of the project’s 99 pin piles and the offshore substation foundation and topside ahead of schedule using the offshore installation vessel Green Jade.

The consortium consisting of Semco Maritime and PTSC M&C was awarded an engineering, procurement, and construction (EPC) contract for the 500 MW offshore substation in 2023.

According to DEME, the combined weight of the offshore substation foundation and topside exceeds 8,000 tons, making it the largest offshore substation installed in Taiwan to date.

With the offshore substation now in place and connected to the export cables, CDWE will continue with the transport and installation of the 33 jacket foundations that will support the project’s Vestas V236-15.0 MW wind turbines. The jacket foundations are being manufactured by Century Wind Power in Taiwan.

Van Oord is responsible for transporting, installing and burying the project’s 33 inter-array cables.

Developed by Copenhagen Offshore Partners (COP) on behalf of Copenhagen Infrastructure Partners (CIP), Fengmiao 1 is located around 35 kilometers off the coast of Taichung.

Fengmiao 1, which reached financial close in 2025 as the first of Taiwan’s Round 3 offshore wind projects, is scheduled to enter commercial operation in 2027.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Business Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Subsea Micropiles to invest £5 million in expanding manufacturing, offshore ops at Scottish port
  2. 2Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  3. 3TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  4. 4TotalEnergies earmarks annual spend of up to $17 billion over next five years

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free