Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›TGE pressing on with construction of third LNG tank at Świnoujście
Clean Fuel

November 8, 2023 · about 2 years ago

TGE pressing on with construction of third LNG tank at Świnoujście

TGE Gas Engineering, an EPC contractor for the storage and handling of liquefied gases, is advancing the construction of the third LNG tank as part of the expansion project of the LNG terminal in Świnoujście, Poland. TGE Gas is building the LNG tank in consortium with Polish construction company POR

2 minutes read
  • LinkedIn
  • X
  • Email
TGE pressing on with construction of third LNG tank at Świnoujście
Courtesy of TGE Gas Engineering

TGE Gas Engineering, an EPC contractor for the storage and handling of liquefied gases, is advancing the construction of the third LNG tank as part of the expansion project of the LNG terminal in Świnoujście, Poland.

TGE Gas is building the LNG tank in consortium with Polish construction company PORR under a $481.7 million contract .

To remind, Polskie LNG, a GAZ-SYSTEM company, was granted a permit to add the 180,000 cubic meter storage tank at the Polish import facility in 2021.

Related Articles

Clean Fuel

Polskie LNG cleared to built third LNG tank at Świnoujście

2 min read

TGE’s scope of work includes basic and detailed design of the LNG storage tank, pumps, interconnecting piping, and boil-off gas treatment, procurement of all equipment, safety procurement of all material, construction of the storage tank within battery limits, and installation of all equipment including in-tank pumps and BOG compressors.

On November 8, 2023, TGE Gas shared an update via social media channels stating that hydrostatic tests were performed on the tank structure and confirmed that the tank was tight.

This content is available after accepting the cookies.

We have reached another milestone in our LNG tank construction Project! The hydrostatic tests performed on the tank structure confirmed that the 180,000 m³ LNG Tank, built by TGE & PORR Polska, is tight. Bravo team TGE & PORR Polska! ??? pic.twitter.com/gHL80sxWDA

“The positive pneumatic and hydrostatic tests are another big step towards completing the extension of the Świnoujście LNG terminal,” the company said.

According to data available on TGE’s website, completion of the project is scheduled for 2024.

Since 2022, the terminal has a commercial regasification capacity of 6.2 billion m3 annually. Once the expansion project is completed, the capacity will increase to 8.3 billion m3 of gas per year, which is expected to cover over 40% of the estimated annual demand of Polish customers.

In March this year, GAZ-SYSTEM’s terminal in Świnoujście received the first delivery of LNG by the Lech Kaczyński, the first LNG carrier built for exclusive use by ORLEN Group.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelFossil EnergyLiquefied Natural GasOther FuelsBusiness Developments & ProjectsInfrastructureStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 122-year Cheniere-Petrobras LNG pact expands energy bridge between North and South America
  2. 2Next chapter of Shell’s Canadian LNG project brings Fluor-JGC JV multibillion-dollar award
  3. 3Subsea production systems for Mozambique’s deepwater LNG project ordered from OneSubsea
  4. 4Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free