Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Cable installation for Shetland HVDC link to resume next month
Cabling

February 24, 2023 · about 3 years ago

Cable installation for Shetland HVDC link to resume next month

NKT is set to commence the second cable installation campaign for SSEN Transmission’s Shetland High Voltage Direct-Current (HVDC) link in the North Sea in March. The £660 million project includes the construction of a 260-kilometer subsea cable from Shetland to the GB mainland, linking Shetland to t

2 minutes read
  • LinkedIn
  • X
  • Email
Cable installation for Shetland HVDC link to resume next month
NKT Victoria

NKT is set to commence the second cable installation campaign for SSEN Transmission’s Shetland High Voltage Direct-Current (HVDC) link in the North Sea in March.

The £660 million project includes the construction of a 260-kilometer subsea cable from Shetland to the GB mainland, linking Shetland to the national grid for the first time.

The installation of the first 100 kilometers of subsea cable was completed at the end of 2022, with all onshore HVDC cables installed for the project.

Related Articles

Cabling

NKT Victoria paces ahead with cable laying for Shetland HVDC link

1 min read

Cable laying vessel NKT Victoria is expected to begin laying the cable as part of Campaign 2, which begins from Weisdale Voe, on 12 March and finish the activities by 10 April.

Once the cable is laid on the seabed, the vessel Grand Canyon III will trench the cable to the required burial depth in the seabed. For any sections that cannot be trenched, rock placement will be undertaken to achieve the required protection.

For the cable pull-in part of the installation works at Weisdale Voe landfall, due to shallow water depth, the cable will be floated into the shore from NKT Victoria. Three workboats will be launched from NKT Victoria along with a fast rescue craft (FRC) that will be utilized to support the pull-in operation.

All the work is planned to be completed by 13 October.

Related Articles

Cabling

Switching station for Shetland HVDC link taking final shape (Video)

2 min read

To remind, NKT secured the €235 million contract from SSEN Transmission in the summer of 2020 to deliver and install an interconnector to the project.

The Shetland HVDC subsea link is expected to be completed by 2024.

SUBSCRIBE

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingSubseaBusiness & FinanceBusiness Developments & ProjectsOutlook & StrategyProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Connecting the offshore energy industry through smarter travel
  2. 2Borr Drilling’s rig trio lines up jobs in Africa and Europe
  3. 3Inpex broadens its Southeast Asian horizons with two offshore blocks
  4. 4Dutch LNG terminal capacity rises to 20 billion cubic meters with 4th tank

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free