Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Commissioning of Baltic Pipe receiving terminal further postponed
Fossil Energy

October 19, 2022 · about 4 years ago

Commissioning of Baltic Pipe receiving terminal further postponed

The commissioning of the Baltic Pipe receiving terminal in western Denmark is set to be further postponed due to continued technical challenges. The receiving terminal for gas from the Norwegian Europipe II pipeline was initially planned to be commissioned on 8 October but was postponed to 20 Octobe

2 minutes read
  • LinkedIn
  • X
  • Email
Commissioning of Baltic Pipe receiving terminal further postponed
Energinet

The commissioning of the Baltic Pipe receiving terminal in western Denmark is set to be further postponed due to continued technical challenges.

The receiving terminal for gas from the Norwegian Europipe II pipeline was initially planned to be commissioned on 8 October but was postponed to 20 October and will now be further delayed for almost two weeks.

Due to continued technical challenges at the terminal in Nybro near Varde, commissioning is now planned to take place in two stages.

First part of the commissioning is expected on 1 November, with half of the total capacity (6,700 MWh/h), while full commissioning is set to take place later this year.

“We still have major technical challenges at the complex facility in Nybro. The challenges include IT systems and the important control and security systems. Unfortunately, we cannot start operations on Thursday as planned. We now consider it a realistic solution that we must start with partial commissioning,” said Torben Brabo , Energinet’s director of International Relations.

According to Energinet, the delay in Nybro will not affect the gas volumes to Poland.

Related Articles

Cabling

Baltic Pipe launches, full start-up expected one month earlier

2 min read

Baltic Pipe was commissioned with partial capacity on 1 October. The volume of gas to Poland will be continuously increased until full commissioning at the end of November.

As previously announced, commissioning at full capacity, up to 10 billion cubic meters of gas per year, can take place before originally planned because the work of laying the last pipelines in the ground in East Jutland and in West Funen progressed faster than expected.

Register for Offshore Energy Exhibition & Conference:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasSubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureOutlook & StrategyProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Shell to take a slice of Equinor's $10 billion oil project in Canada
  2. 2SLB and TotalEnergies enter into 15-year digital drilling agreement
  3. 3World’s first ammonia-powered dry bulk carrier ready for maiden voyage
  4. 4Weatherford expands its scope of work for Equinor

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free