Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Pre-construction survey scheduled for Wales-Ireland interconnector
Cabling

July 11, 2022 · about 4 years ago

Pre-construction survey scheduled for Wales-Ireland interconnector

A pre-construction survey for the Greenlink Interconnector, which will link Wales and Ireland, is set to commence in mid-July. The pre-construction survey is expected to be carried out between 16 July and 2 August, weather dependent. The work will be conducted by the GEOxyz-owned multi-disciplined s

2 minutes read
  • LinkedIn
  • X
  • Email
Pre-construction survey scheduled for Wales-Ireland interconnector
Greenlink Interconnector Ltd.

A pre-construction survey for the Greenlink Interconnector, which will link Wales and Ireland, is set to commence in mid-July.

The pre-construction survey is expected to be carried out between 16 July and 2 August, weather dependent.

The work will be conducted by the GEOxyz-owned multi-disciplined survey vessel Geo Ocean V. Running on hybrid propulsion, the vessel is fitted for geophysical and geotechnical survey work.

Related Articles

Cabling

Jan De Nul to install Greenlink Interconnector

2 min read

Greenlink is known as the first privately-financed interconnector in Europe supported under the Cap and Floor regulatory regimes in the UK and Ireland and represents a total investment of over €500 million.

It comprises a 190-kilometer subsea and underground HVDC cable system, two converter stations, a tail station at Great Island in Wexford, Ireland, and onshore cable works in Wexford and Pembrokeshire, Wales.

The consortium of Sumitomo Electric and Siemens Energy was contracted in September 2021 to provide the design, engineering, procurement, production, construction, and commissioning of an HVDC subsea/underground electricity interconnector cable, with associated converter stations.

Earlier this year, Jan De Nul won a contract with Sumitomo Electric Industries for the installation of two subsea HVDC cables and one fiber optic cable for the Greenlink Interconnector.

The project reached a financial close in March, enabling the start of full construction of the electricity interconnector after Partners Group, which owns Greenlink on behalf of its clients, secured debt financing for the project with a consortium of banks to fund construction.

The interconnector is due for commissioning in 2024.

Register for Offshore Energy Exhibition & Conference:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingSubseaSurveys & InterventionsBusiness & FinanceBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Vår Energi bolsters its oil & gas portfolio with wrap-up of Pandion buy
  2. 2LNG-to-FSRU conversion widening Karpowership-backed Kinetics’ gas infrastructure fleet
  3. 3Potential for tidal lagoon in South East Wales being explored
  4. 4After Fugro, TDI-Brooks selected for surveys offshore Timor-Leste

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free