Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Surveys scheduled at Pentland floating wind project
Offshore Wind

June 18, 2021 · about 5 years ago

Surveys scheduled at Pentland floating wind project

MMT and SEP Hydrographic are set to conduct the geophysical and environmental survey at the Pentland floating offshore wind project in Scotland. Geophysical and environmental survey work will be carried out in the offshore areas and coastal sea areas west of the Pentland Firth. MMT will conduct the

1 minutes read
  • LinkedIn
  • X
  • Email
Surveys scheduled at Pentland floating offshore wind project
Credits to KIS-ORCA

MMT and SEP Hydrographic are set to conduct the geophysical and environmental survey at the Pentland floating offshore wind project in Scotland.

Geophysical and environmental survey work will be carried out in the offshore areas and coastal sea areas west of the Pentland Firth.

MMT will conduct the geophysical survey in the offshore area north of Dounreay. It will be conducted with a hull-mounted multibeam sonar with towed ROTV mounted sidescan sonar, sub-bottom profiler, and tethered magnetometer. Additionally, a seismic sparker will be towed behind the vessel.

The total geophysical survey is planned for approximately 31 days, but poor weather may extend these dates.

SEP Hydrographic will carry out the nearshore export route survey using survey vessel Pulsar from 21 June.

The work will commence from the 10-meter Contour working towards the nearshore. It will be conducted with a pole-mounted multibeam sonar with towed side-scan sonar, sub-bottom profiler, and magnetometer.

The total survey is planned for approximately 15 days, but it is weather dependant.

The Pentland wind farm, developed by Copenhagen Infrastructure Partners (CIP), is expected to feature up to ten 10-16 MW turbines that will make a total capacity of up to 100 MW.

Construction is planned to begin upon financial close in 2024, with commissioning scheduled for 2026.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindSubseaSurveys & InterventionsWind FarmsBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 122-year Cheniere-Petrobras LNG pact expands energy bridge between North and South America
  2. 2Next chapter of Shell’s Canadian LNG project brings Fluor-JGC JV multibillion-dollar award
  3. 3Subsea production systems for Mozambique’s deepwater LNG project ordered from OneSubsea
  4. 4Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free