Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Deepwater Installation›Serica preparing to bring third Rhum well online
Deepwater Installation

June 10, 2021 · about 5 years ago

Serica preparing to bring third Rhum well online

Serica Energy has completed a flow test on the Rhum R3 well in the UK North Sea with plans to start production in the third quarter of 2021.

2 minutes read
  • LinkedIn
  • X
  • Email
Bruce field - Serica Energy
Bruce field; Source: Serica Energy

Following intervention work, Serica Energy has completed a flow test on the Rhum R3 well in the UK North Sea with plans to start production in the third quarter of 2021.

Rhum is a gas condensate field producing from two subsea wells, R1 and R2, tied into the Bruce facilities through a 44-kilometre pipeline. The third well, R3, required intervention work before it could be brought online.

In an operational update for the Rhum R3 well, Serica said on Thursday that the new completion equipment has been successfully installed into R3 and a flow test has now been performed. A stabilised flow rate of 58.4mmscf/d of gas and 135bbls/d of condensate has been achieved through a 60/64ths inch choke.

This rate was constrained by the surface well test equipment onboard the WilPhoenix semi-submersible drilling rig and it is expected that the well will be able to produce at higher rates when in production. Serica contracted the Awilco Drilling-owned rig WilPhoenix for Rhum ops back in May 2020.

The rig started working on the Rhum field R3 project in October 2020 but experienced technical problems as well as weather delays, incurring additional costs to Serica for the project.

Related Articles

Fossil Energy

Serica suffers Rhum delays due to Awilco rig downtime and weather

3 min read

Serica also stated that a diving support vessel (DSV) has been contracted to install the subsea control equipment required so the well can start producing in 3Q 2021.

The successful recompletion of R3 will increase the Rhum production capacity utilising the existing facilities located on the Bruce platform. Serica has also recently extended the life of Bruce field through to 2030.

In related news, Serica in May 2021 encountered difficulties while drilling its Columbus well in the UK North Sea. As a result of additional operations, the Columbus well will take longer and cost more than expected, but will not affect the timing of the first production. The well is being drilled using a Maersk Drilling-owned jack-up rig, the Maersk Resilient.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Deepwater InstallationFossil EnergyOil & GasRigsSubseaBusiness & FinanceBusiness Developments & ProjectsExploration & ProductionVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects
  2. 2Tekmar nets €6 million contract extension in offshore wind
  3. 3Japanese shipping major enters CCS realm in Norway
  4. 4Shell bets big on Canada with go-ahead for LNG project expansion, doubling capacity to 28 mtpa

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free