Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Cable connection needed for German offshore platform
Cabling

June 2, 2021 · about 5 years ago

Cable connection needed for German offshore platform

Transmission system operator TenneT has issued a notice for a turnkey contract covering the cable system needed to connect the BorWin6 offshore platform to the German grid. With the 930 MW BorWin6 project, TenneT is planning a direct current connection in the North Sea Cluster 7. Scheduled to be com

1 minutes read
  • LinkedIn
  • X
  • Email
Cable connection needed for German offshore platform
TenneT/Illustration

Transmission system operator TenneT has issued a notice for a turnkey contract covering the cable system needed to connect the BorWin6 offshore platform to the German grid.

With the 930 MW BorWin6 project, TenneT is planning a direct current connection in the North Sea Cluster 7.

Scheduled to be commissioned by 2027, the BorWin6 offshore grid connection will collect the three-phase current generated at an offshore wind farm to be selected in the 2022 auction round.

The three-phase current will then be converted into the direct current on the BorWin kappa offshore converter platform and transported to the mainland in Büsum via an export cable approximately 189 kilometres in length.

From there, the electricity is to be transported to the BUTL grid connection point near Büttel via an approximately 46-kilometre underground cable.

The content of this tender is the turnkey and ready-to-use construction of the entire DC cable system required for this, TenneT said.

The cable system consists of two DC single conductor submarine cables, two DC single conductor land cables, optical fibers, sleeves, and cable terminations.

In addition, the scope of delivery and performance of the cable system includes its design, manufacture, delivery, construction, installation and commissioning as well as all systems, ancillary systems and components that are required for safe and highly available operation of the cable system.

The tender remains open until 14 July. The contract will have a duration of 64 months.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingGridOffshore WindSubseaBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Shell bets big on Canada with go-ahead for LNG project expansion, doubling capacity to 28 mtpa
  2. 2Black Sea mega-project narrows first gas window to early 2027 with work in final execution stage
  3. 3New JV set up in Nigeria for work with TotalEnergies and other oil & gas majors
  4. 4Subsea Micropiles to invest £5 million in expanding manufacturing, offshore ops at Scottish port

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free