Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Ørsted books Wind Innovation SOV for Hornsea Two offshore wind farm
Offshore Wind

February 5, 2021 · about 5 years ago

Ørsted books Wind Innovation SOV for Hornsea Two offshore wind farm

C-bed has signed a contract with Ørsted for the deployment of its Service Operation Vessel (SOV) Wind Innovation on the Hornsea Two offshore wind farm in the UK. The vessel, which has also been hired for Ørsted’s Hornsea One offshore wind farm and is currently in full operation there, will start wor

1 minutes read
  • LinkedIn
  • X
  • Email
The Wind Innovation SOV vessel
C-bed

C-bed has signed a contract with Ørsted for the deployment of its Service Operation Vessel (SOV) Wind Innovation on the Hornsea Two offshore wind farm in the UK.

The vessel, which has also been hired for Ørsted’s Hornsea One offshore wind farm and is currently in full operation there, will start working at the Hornsea Two offshore wind farm as of March. There, the SOV will be providing the daily logistics and accommodation for the personnel working on the cable termination project.

During the project, C-bed will use the Port of Immingham as the base port for crew change and loading of fresh supplies.

Hornsea Project One was commissioned in January 2020, when it became the world’s largest offshore wind farm. The 1.2 GW project comprises 174 Siemens Gamesa 7 MW turbines installed some 120 kilometres off Yorkshire.

On Hornsea Two, construction is now well underway, after the first foundation and the jacket for offshore substation were installed in October 2020.

The 1.4 GW offshore wind farm, scheduled for commissioning in 2022, will comprise 165 Siemens Gamesa 8 MW turbines, installed in the waters some 89 kilometres north-east of Grimsby.

Once operational, Hornsea Two will become the biggest operational offshore wind farm in the world, producing enough electricity to supply over 1.3 million homes in the UK with green energy.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Eni sheds partial stakes in Indonesian gas assets as Pertamina and Medco bolster portfolios
  2. 2New wind for hydrogen-electric shipping as GMI-PowerCell collaboration expands to four bulk carriers
  3. 3AI, next-gen tech, and maritime decarbonization on RINA- China Merchants Energy Shipping pact’s agenda
  4. 4Stena Drilling’s 18-year-old drillship is on its way to Namibia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free