Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›Borssele 1+2 construction team not skipping a beat
Offshore Wind

May 14, 2020 · about 6 years ago

Borssele 1+2 construction team not skipping a beat

Ørsted has provided an update on the ongoing offshore construction work at the 752 MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, saying that all activities are going according to plans. So far, DEME’s installation vessel Innovation has installed 73 out of the 94 monopile foundations a

1 minutes read
  • LinkedIn
  • X
  • Email
Borssele 1+2 construction team not skipping a beat
DEME Group

Ørsted has provided an update on the ongoing offshore construction work at the 752 MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, saying that all activities are going according to plans.

So far, DEME’s installation vessel Innovation has installed 73 out of the 94 monopile foundations at the site some 23 kilometres off the coast of Zeeland.

The installation of the Nexans inter-array cables has reached a halfway point. Van Oord has installed 47 out of the 94 inter-array cables. Van Oord has deployed its dedicated cable-laying vessel Nexus and the trencher Dig-It to install and bury the 94 inter-array cables to a depth of 2 metres.

The wind farm’s first foundation was installed mid-January and the first inter-array cable was put in place at the end of February.

The installation of the wind farm’s turbines started in mid-April. So far, DEME’s jack-up Sea Challenger has installed eleven out of the 94 Siemens Gamesa 8 MW units. The wind farm delivered its first power at the end of April.

Borssele 1+2 is expected to be completed by the end of 2020 when it will become the largest offshore wind farm in the Dutch North Sea.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1122-meter subsea vessel continues charter with Reach Subsea through March 2028
  2. 2VARD opens new office in Vietnam, plans to grow to 40+ engineers
  3. 3$860M play for offshore oil assets powers Ithaca’s entry into Canadian energy game
  4. 4$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free