Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›COVID-19 prolongs Norfolk Boreas OWF examination process
Offshore Wind

May 12, 2020 · about 6 years ago

COVID-19 prolongs Norfolk Boreas OWF examination process

The deadline for the close of the examination period for Vattenfall’s Norfolk Boreas offshore wind farm has been pushed back to 12 October 2020. The UK Planning Inspectorate submitted a request to extend the examination period for the Norfolk Boreas development consent order (DCO) application to the

2 minutes read
  • LinkedIn
  • X
  • Email
A photo of a turbine at Vattenfall's offshore wind farm
Vattenfall

The deadline for the close of the examination period for Vattenfall’s Norfolk Boreas offshore wind farm has been pushed back to 12 October 2020.

The UK Planning Inspectorate submitted a request to extend the examination period for the Norfolk Boreas development consent order (DCO) application to the Department for Business, Energy and Industrial Strategy (BEIS) on 6 April 2020.

The examining authority cited reasons related to the effects of the COVID-19 pandemic as those affecting the process.

Namely, several hearings needed to be cancelled, potentially resulting in interested parties not being given a fair opportunity to participate in the examination, according to the Planning Inspectorate.

Furthermore, a number of interested parties no longer had the capacity to participate in the examination process as a result of COVID-19 resource prioritisation.

The Secretary of State approved the extension of the deadline on 11 May.

Still, the Planning Inspectorate is expected “to make best efforts to complete the examination process as soon as is reasonably practicable within the extended period” .

The inspectorate will publish a new examination process timetable by 19 May.

Vattenfall submitted the DCO applicationon 11 June, with the Planning Inspectorate accepting the application the following month.

The examination process of the Norfolk Boreas DCO began in November 2019.

Norfolk Boreas is a 1.8 GW offshore wind project located next to sister project Norfolk Vanguard . It covers an area of 725 square kilometres and is located circa 72 kilometres off the Norfolk coast at its nearest point.

The project will feature up to 180 turbines with a minimum individual capacity of 10 MW, installed on fixed bottom foundations.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsAuthorities & GovernmentProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Seatrium picks up 9th FSRU conversion job with Karpowership
  2. 2122-meter subsea vessel continues charter with Reach Subsea through March 2028
  3. 3VARD opens new office in Vietnam, plans to grow to 40+ engineers
  4. 4$860M play for offshore oil assets powers Ithaca’s entry into Canadian energy game

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free