Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›All turbines up at Northwester 2
Offshore Wind

April 15, 2020 · about 6 years ago

All turbines up at Northwester 2

Jan De Nul has completed the installation of MHI Vestas 9.5 MW turbines at the Northwester 2 offshore wind farm.

1 minutes read
  • LinkedIn
  • X
  • Email
The vessel Vole au vent at Northwester 2 offshore wibd farm, installing wind turbines
Jan De Nul

Jan De Nul has completed the installation of MHI Vestas 9.5 MW turbines at the Northwester 2 offshore wind farm.

The Vole au vent turbine installation vessel started offshore works in December 2019. A second installation vessel, the Seajacks Scylla, joined Vole au vent in mid-March.

Namely, adverse weather in the first months slowed down the pace of the installation works. The project team then deployed the Scylla to accelerate the operations.

“Upon securing a second installation vessel to make up for the time lost in the first months of the year, the COVID-19 crisis broke out threatening to undo all our efforts”, said Peter Caluwaerts, Parkwind’s Project Director. “However, the extraordinary dedication we witnessed from the different teams, in the midst of an unprecedented context and with all additional safety measures, has been humbling.”

Parkwind’s 219 MW wind farm is the first project to use the V164-9.5 MW wind turbines in commercial operation.

The turbine supplier, MHI Vestas, also holds a 15-year turbine service agreement for the offshore wind farm.

The first of the total of 23 wind turbines at Northwester 2 produced first power in January 2020.

All major turbine components have been assembled and pre-commissioned in the Flushing marshaling harbor.

The Vole au vent vessel also installed all monopile foundations at the project site some 50 kilometres off the coast of Ostend in Belgium.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Baker Hughes helping chart a course for LNG and monetize Venezuela’s gas reserves
  2. 2Yinson Production and Eni amplifying African FPSO’s gas capacity
  3. 3Sea Lion project on the hunt for new contractors amid Argentine sanction threats
  4. 4Seatrium picks up 9th FSRU conversion job with Karpowership

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free