Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›SSEN Wraps Up Jura – Mainland Cable Works
Subsea

April 2, 2020 · about 6 years ago

SSEN Wraps Up Jura – Mainland Cable Works

Scottish and Southern Electricity Networks (SSEN) has replaced the submarine electricity cable connecting the Isle of Jura to Tayvallich in Argyll, following a cable fault in November. SSEN connected the new cable to the main electricity network on Tuesday 31 March, returning the network to normal o

1 minutes read
  • LinkedIn
  • X
  • Email
SSEN Wraps Up Jura – Mainland Cable Works

Scottish and Southern Electricity Networks (SSEN) has replaced the submarine electricity cable connecting the Isle of Jura to Tayvallich in Argyll, following a cable fault in November.

SSEN connected the new cable to the main electricity network on Tuesday 31 March, returning the network to normal operation to ensure a electricity supply to the islands of Jura, Islay and Colonsay.

Despite securing a marine licence to carry out the cable replacement in January, cable installation was delayed by continued unfavourable weather conditions.

The vessel remained on standby and was mobilised at first light on Wednesday 25 March to begin installation, with SSEN’s regional teams making final connections to energise the cable on Tuesday 31 March.

Since November, Jura, Islay and Colonsay have been powered by a combination of Bowmore Power Station and local renewable generation to ensure the islands continued to receive the power.

Mark Rough , SSEN’s director of Customer Operations, said: “Adverse weather conditions, including Storms Brendan, Ciara and Dennis, presented our teams with various challenges along the way, but I’d like to thank everyone involved, from our subsea teams, contract partners and renewable generators; to our colleagues working on the islands, Bowmore Power Station, and our control room for their continued efforts to help return the network to normal operation as soon as possible.”

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Houston-based subsea services provider finds local partner in Brazil
  2. 2JERA deepens Australian LNG foothold with larger stake in Chevron’s project
  3. 3MoU charts the path for tidal and ocean current energy projects in Chile
  4. 4Seadrill hit with $55 million bill after appeals court upholds rig breach ruling

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free