Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›NOPSEMA Assesses Tasmanian Gas Pipeline Offshore Environment Plan
Subsea

October 16, 2019 · about 7 years ago

NOPSEMA Assesses Tasmanian Gas Pipeline Offshore Environment Plan

National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) has started the assessment of the Tasmanian Gas Pipeline offshore environment plan. The Tasmanian Gas Pipeline (TGP) is a natural gas transmission pipeline system that extends from Longford in Victoria, across Bass S

1 minutes read
  • LinkedIn
  • X
  • Email

National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) has started the assessment of the Tasmanian Gas Pipeline offshore environment plan.

The Tasmanian Gas Pipeline (TGP) is a natural gas transmission pipeline system that extends from Longford in Victoria, across Bass Strait to Bell Bay in north-east Tasmania. Additional onshore pipelines extend from Bell Bay to Port Latta in north-west Tasmania and to Bridgewater in the south.

The offshore TGP is approximately 301 km in length, with maximum water depth along the route of approximately 77 meters. The offshore TGP route was selected to minimize pipeline length and avoid adverse seafloor conditions and on bottom obstructions.

There are two drilled crossings where the pipeline meets the Victorian and Tasmanian landfalls, which were constructed using horizontal directional drilling (HDD). The Victorian HDD section is 1080 m long, exiting the seabed at approximately 10 m water depth.

The Victorian shore approach was trenched and backfilled naturally. The Tasmanian HDD section is 859 m long entering the seabed in 10.5m water depth.

The rest of the offshore component of the TGP was installed on the Bass Strait seabed but has self-buried to various extents along parts of the route.

ROV surveys of the pipeline, to assess pipeline integrity and any maintenance requirements, are undertaken on a periodic basis and occur approximately every 5 to 8 years.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free