Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Eni begins Coral Sul FLNG hull installation works
Clean Fuel

July 22, 2019 · about 7 years ago

Eni begins Coral Sul FLNG hull installation works

Italian energy giant Eni has started installation works on the hull of the Coral Sul floating liquefied natural gas (FLNG) treatment and liquefaction unit that will be moored offshore in Mozambique.

2 minutes read
  • LinkedIn
  • X
  • Email

Italian energy giant Eni has started installation works on the hull of the Coral Sul floating liquefied natural gas (FLNG) treatment and liquefaction unit that will be moored offshore in Mozambique.

The unit is part of the Coral South project, which will put in production 450 billion cubic meters of gas from the giant Coral reservoir, Eni said in a statement on Monday.

The hull is expected to be launched in 2020, in line with the planned production startup of the Coral South project in 2022.

The Coral Sul FLNG facility will have a gas liquefaction capacity of 3.4 million tons per year when completed. The facility will be anchored at a water depth of around 2,000 meters by means of 20 mooring lines that weigh a combined 9,000 tons.

Construction works on the Coral Sul FLNG started in 2018 and are ongoing in seven operational centers.

Construction of the mooring turret began in March; construction of the hull’s 24 modules that contain the LNG storage tanks and sections of the treatment facilities began in September. Construction of the topside, consisting of 12 gas treatment and LNG modules, started last November, along with the living-quarters.

By the end of 2019, the overall progress of the project is expected to exceed 60 percent completion, Eni said.

Drilling and completion activities for the six subsea wells that will feed the liquefaction unit will begin in September 2019. The wells will have an average depth of approximately 3000 meters and will be drilled in about 2000 meters of water depth.

The activities, carried out by the Saipem 12000 drilling rig, will be completed by the end of 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Woodside passes the baton for offshore gas project to Timor Gap in $200 million deal
  2. 2Fugro wins UXO survey contract for German offshore grid connections
  3. 3Accelerating operational excellence in offshore energy
  4. 4Go-ahead for North Sea wildcat clears path for Equinor’s drilling ops with COSL rig

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free