Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Tipner Lake Works to Resume Next Week
Dredging

March 29, 2019 · about 7 years ago

Tipner Lake Works to Resume Next Week

Following the winter break, works on the North Portsea Island Coastal Flood Defense Scheme are due to start again next week, informs the Eastern Solent Coastal Partnership (ESCP). Work will be restarting on site for the North Portsea Island project at Tipner from April 1st, said ESCP in its latest u

1 minutes read
  • LinkedIn
  • X
  • Email

Following the winter break, works on the North Portsea Island Coastal Flood Defense Scheme are due to start again next week, informs the Eastern Solent Coastal Partnership (ESCP).

Work will be restarting on site for the North Portsea Island project at Tipner from April 1st, said ESCP in its latest update.

During the winter period, the construction works stopped to avoid disturbance to birds that used the harbor from October to March each year.

According to ESCP, the remaining work includes the construction of a new rock and concrete sloped wall by Ports Bridge roundabout, as well as ground raising, tarmacking and landscaping in specific areas.

The Tipner Lake scheme is part of a five-phase project to help protect the whole of North Portsea Island from coastal flooding for the next century.

In total, these phases cover 8.4km of coastline which will help to protect 4,500 homes, 500 businesses and important infrastructure.

Overall, the North Portsea Island Coastal Flood Defense Scheme has been split into five phases of works, with phases 1 (Anchorage Park) and 2 (Milton Common) already complete.

Phase 3 (Tipner Lake) is due for full completion in late summer 2019. This will be followed by Phase 4 (Kendall’s Wharf & Eastern Road) and Phase 5 (Ports Creek).

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Shell to take a slice of Equinor's $10 billion oil project in Canada
  2. 2SLB and TotalEnergies enter into 15-year digital drilling agreement
  3. 3World’s first ammonia-powered dry bulk carrier ready for maiden voyage
  4. 4Weatherford expands its scope of work for Equinor

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free