Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Ponce de Leon Inlet Dredging Schedule Updated
Dredging

December 21, 2018 · about 7 years ago

Ponce de Leon Inlet Dredging Schedule Updated

The U.S. Army Corps of Engineers announced yesterday schedule changes to maintenance dredging of Ponce de Leon Inlet and pumping sediment to the near-shore of New Smyrna Beach in Volusia County. The near-shore work naturally nourishes the beach via wave action, which then helps reduce risk to landsi

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers announced yesterday schedule changes to maintenance dredging of Ponce de Leon Inlet and pumping sediment to the near-shore of New Smyrna Beach in Volusia County.

The near-shore work naturally nourishes the beach via wave action, which then helps reduce risk to landside infrastructure.

The Corps’ contractor, Cavache, Inc. of Pompano Beach Florida, will not conduct operations Dec. 24-26, and Dec. 31 – Jan. 1. The team will work a day shift only, about 10-12 hours daily, Dec. 27-30, reported the Corps.

Starting Jan. 2, Cavache will return to 24-hour operations daily until project completion.

According to the Project Manager Beau Corbett, inclement weather has delayed operations since the project started in August. Working 24 hours daily is required to complete the project on schedule.

“ The operational changes support the local community as well as the contractor during the holiday period. We’ll transition back to 24-hour operations after the holidays to get the work completed by April 30 ,” Corbett said.

If the weather cooperates, the Corps anticipates the booster pump currently located “in the river” in the vicinity of Beachway Avenue, New Smyrna Beach, will be relocated to the south of the island in the vicinity of Crawford Road. It will remain at this location until the end of the project, operating 24-7.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Eni sheds partial stakes in Indonesian gas assets as Pertamina and Medco bolster portfolios
  2. 2New wind for hydrogen-electric shipping as GMI-PowerCell collaboration expands to four bulk carriers
  3. 3AI, next-gen tech, and maritime decarbonization on RINA- China Merchants Energy Shipping pact’s agenda
  4. 4Stena Drilling’s 18-year-old drillship is on its way to Namibia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free