Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Trianel Windpark Borkum II Foundations In Place
Wind Farms

December 3, 2018 · about 7 years ago

Trianel Windpark Borkum II Foundations In Place

All 32 turbine foundations for the 200MW Trianel Windpark Borkum II offshore wind farm have been installed at the construction site some 45 kilometers north of the island of Borkum in the German North Sea. “We are right on schedule with the construction of the offshore wind farm. We were able to com

1 minutes read
  • LinkedIn
  • X
  • Email

All 32 turbine foundations for the 200MW Trianel Windpark Borkum II offshore wind farm have been installed at the construction site some 45 kilometers north of the island of Borkum in the German North Sea.

“We are right on schedule with the construction of the offshore wind farm. We were able to compensate for the partly difficult weather conditions during the first construction phase,” said Irina Lucke , Technical Director of Trianel Windkraftwerk Borkum II GmbH & Co. KG.

At the moment, the inter-array cable system is being laid and the turbine foundations are getting connected to the transformer substation. The construction works will be continued during the winter.

The beginning of the next phase of construction is planned for the spring of 2019. The 32 Senvion 6.2M 152 Power Upgrade offshore wind turbines will be installed in the North Sea by autumn 2019.

The Jan De Nul jack-up vessel Vole au vent will be in operation for this task and the base harbour for the construction works is Eemshaven in the Netherlands.

The first of a total of 64 tower segments and 96 rotor blades were already shipped there. In the months to come, the further components, such as the 32 nacelles with pre-assembled rotor hubs will follow.

Photos: TWBII

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1XOCEAN enters strategic alliance in Japan to expand use of USVs
  2. 2Fresh North Sea gas discovery yields up to 10 million barrels of oil equivalent
  3. 3Rockhopper pledges $44 million for oil project’s second Falklands-bound FPSO
  4. 4Valaris rigs find more work in North Sea, Australia, and Suriname

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free