Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›PHOTO: Equipment Begins to Arrive at Fernandina Beach
Dredging

November 16, 2018 · about 8 years ago

PHOTO: Equipment Begins to Arrive at Fernandina Beach

Manson Construction crews have begun staging equipment for the upcoming Nassau County project at Fernandina Beach. According to the Army Corps’ Jacksonville District, maintenance dredging of U.S. Naval Station Kings Bay and sand placement at Fernandina Beach and Fort Clinch State Park is anticipated

1 minutes read
  • LinkedIn
  • X
  • Email

Manson Construction crews have begun staging equipment for the upcoming Nassau County project at Fernandina Beach.

According to the Army Corps’ Jacksonville District, maintenance dredging of U.S. Naval Station Kings Bay and sand placement at Fernandina Beach and Fort Clinch State Park is anticipated to begin mid-December.

The Corps estimates that the contractor will place about 340,000 cubic yards at Fernandina Beach and 170,000 cubic yards at Fort Clinch State Park, with approx 930,000 cubic yards of non-beach compatible sand between the approved nearshore disposal area and an offshore disposal site.

The City of Fernandina Beach reported yesterday that the fusing stations for the beach renourishment project have been set based on operational considerations and minimal impact on homes.

“ One is between the Fort Clinch boundary and Beach Access 16 North, the other is just south of Beach Access 6. There will be significant and constant equipment and vehicles on the beach for the next few months ,” the City said.

The dredging and beach renourishment is expected to last for approximately three months. USACE also added that the works will end before March 31, which is the end of the environmental turtle window allowing hopper dredging.

Sponsored by the Naval Submarine Base Kings Bay and the City of Fernandina Beach, the project is critical to commercial cargo transiting the port and also to the Navy base, which shares the entrance channel.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1JERA deepens Australian LNG foothold with larger stake in Chevron’s project
  2. 2MoU charts the path for tidal and ocean current energy projects in Chile
  3. 3Seadrill hit with $55 million bill after appeals court upholds rig breach ruling
  4. 4Sunda steps closer to dusting off 1985 gas field as New Zealand bid goes exclusive

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free