Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Buffalo South Breakwater Repairs on the Way
Dredging

September 7, 2018 · about 8 years ago

Buffalo South Breakwater Repairs on the Way

The U.S. Army Corps of Engineers, Buffalo District recently awarded a contract to Ryba Marine Construction to repair a portion of the Buffalo South breakwater. The 10,200-foot Buffalo South breakwater protects the Buffalo Harbor and nearby dredged sediment confined disposal facilities. The south bre

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Buffalo District recently awarded a contract to Ryba Marine Construction to repair a portion of the Buffalo South breakwater.

The 10,200-foot Buffalo South breakwater protects the Buffalo Harbor and nearby dredged sediment confined disposal facilities.

The south breakwater is exposed to deep water wave and ice action, which has caused a 1,000-foot section at the south end to breakdown and unravel.

“ Navigation is one of the Corps of Engineers’ earliest Civil Works missions ,” said USACE, Buffalo District Commander Lt. Col. Jason Toth . “ The investment to repair a degraded reach of the Buffalo South breakwater will ensure safe navigation for vessels and protect the harbor.”

According to the Corps, they will use work plan funding from fiscal years 2017 and 2018 for the repair project.

The awarded contract covers 325 feet of the 1,000 feet of critical repair. There are two options that could repair another 225 feet of the breakwater under the current contract, if fiscal year 2019 work plan funding is received. The remaining 450 feet of critical repair could be funded in the fiscal year 2019 work plan or a future work plan.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon