Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›August Update for IJmuiden Sea Lock Project
Dredging

August 21, 2018 · about 8 years ago

August Update for IJmuiden Sea Lock Project

During this month, OpenIJ will – under the New IJmuiden Sea Lock project – continue working on the walls of the inner lock head and on the flood defenses. Near the outer lock head, OpenIJ is carrying out excavation work for the lock sill cofferdam, reported the Port of Amsterdam. At the inner lock h

2 minutes read
  • LinkedIn
  • X
  • Email

During this month, OpenIJ will – under the New IJmuiden Sea Lock project – continue working on the walls of the inner lock head and on the flood defenses.

Near the outer lock head, OpenIJ is carrying out excavation work for the lock sill cofferdam, reported the Port of Amsterdam.

At the inner lock head, OpenIJ is still working hard on the installation of reinforcement steel for the walls. The builders are currently busy with concreting stages 3 and 4 for the walls at a height of 13 meters above NAP (Normal Amsterdam Level), the Port said.

The officials also added that the walls of the inner lock head will be constructed in seven stages in total. The reinforcement steel for the walls of the inner lock head has already been installed up to a height of 18 meters above NAP.

Two lock gates will be installed into the inner lock head, namely the gate on the North Sea Canal side (the inner gate) and the spare lock gate.

Also in August, work will continue on the future flood defenses. The height of the flood defense will be 8.85 meters above NAP. Contracting consortium OpenIJ is currently working on the walls of the flood defense. The future public road will be built on top of the flood defense.

At the moment, OpenIJ is carrying out excavation work for the lock sill cofferdam next to the outer lock head. In this cofferdam, the lock sill is being built on which the future outer gate will run for closing and opening the lock, concluded the Port of Amsterdam.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free