Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Inpex confirms end-September for Ichthys LNG shipments start
Clean Fuel

July 11, 2018 · about 8 years ago

Inpex confirms end-September for Ichthys LNG shipments start

Japan’s Inpex said the shipment of products from the Ichthys LNG project in Australia will start by the end of September, following new delays.

2 minutes read
  • LinkedIn
  • X
  • Email

Japan’s Inpex said the shipment of products from the Ichthys LNG project in Australia will start by the end of September, following new delays.

The company said on Wednesday it has completed the inspection on electrical equipment during the final safety verifications carried out in cooperation with Australian regulators as it prepares to start production.

Ichthys LNG project has already completed the necessary commissioning of all key onshore and offshore facilities for the production start-up.

To remind, Australia’s National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) found issues at the Ichthys LNG project’s CPF during an inspection.

Inpex noted in its statement, that following additional verifications concerning the electrical equipment, the project is scheduled to commence production, and will thereafter begin the shipment of products towards the end of the first half of the current fiscal year, ending September 2018.

The company also noted that first, it will start shipping condensate followed by liquefied natural gas and then liquefied petroleum gas (LPG).

However, it still noted that the Ichthys LNG activity schedule may fluctuate depending on the weather conditions at the worksites, preparation activities and other factors.

Inpex added it is also evaluating how the delays will impact the company’s financial results for the year ending March 2019.

Reuters reported last week the project value was pushed up by the delays from the initial $34 billion to around $40 billion.

The Ichthys LNG project is expected to produce up to 8.9 million tonnes of LNG and 1.6 million tons of LPG at peak annually, with up to 100,000 barrels of condensate per day at peak.

The project is a joint venture between Inpex, major partner Total, Taiwan’s CPC Corporation and the Australian subsidiaries of Tokyo Gas, Osaka Gas, Kansai Electric, Chubu Electric Power and Toho Gas.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Mazarine taking the helm at Black Sea Oil & Gas as Carlyle and EBRD exit
  2. 2CNOOC’s 2026 run powered by 9 start-ups, 5 new oil & gas discoveries, and 23 appraisals
  3. 3Solstad vessel nets two subsea contracts in Asia Pacific
  4. 4Noble rigs’ $560 million drilling gigs push fleet backlog to $6.7 billion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free