Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Spain Gets Its First Offshore Wind Turbine
Wind Farms

June 21, 2018 · about 8 years ago

Spain Gets Its First Offshore Wind Turbine

The 5MW Elisa self-installing telescopic offshore wind turbine, developed under the EU-funded Elican project, arrived at its designated location at the Plocan site off Gran Canaria today, 21 June.

2 minutes read
  • LinkedIn
  • X
  • Email

The 5MW Elisa self-installing telescopic offshore wind turbine, developed under the EU-funded Elican project, arrived at its designated location at the Plocan site off Gran Canaria today, 21 June.

?? Prototipo de aerogenerador marino de proyecto Elican liderado @esteyco ya en el Banco Ensayos @plocan ?? Prototype Marine Wind Turbine for the Elican project led by @esteyco already @plocan Test Site pic.twitter.com/VFztprhbxk

— Plataforma Oceánica de Canarias (PLOCAN) (@plocan) June 21, 2018

The Elisa technology allows the turbine tower and the wind turbine to be fully assembled in port, eliminating the need for large vessels or cranes during the installation.

The prototype’s nacelle and blades were mounted on the telescopic tower in April 2018. The following month, an auxiliary flotation system was attached to the unit to increase the stability during the transportation and installation of the turbine.

The auxiliary system was designed and built after the Elican consortium received a EUR 2.4 million grant from Spanish Centre for the Development of Industrial Technology (CDTI) in March. The grant has supported the design and construction of the platform for Transportation (T), Installation (I) and Maintenance (M) of gravity offshore structures, and coupling the TIM demonstrator project with Elican.

The Elisa/Elican project is led by Esteyco within a consortium also including Siemens Gamesa, ALE Heavylift, DEWI GmbH, and Plocan.

The project’s goal, which is now achieved, was to assemble the entire system – including the foundation, tower and wind turbine – and its pre-commissioning under controlled conditions at the Arinaga port, and then tow it to the site using conventional tugs.

According to the developer, this reduces the risks associated with assembly work at sea and can cut installation costs by 30% to 40% compared to existing conventional solutions.

Offshore WIND Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsResearch & DevelopmentTechnology

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1World’s first ammonia-powered dry bulk carrier ready for maiden voyage
  2. 2Weatherford expands its scope of work for Equinor
  3. 3Offshore installation starts at Valeura's Gulf of Thailand field ahead of schedule
  4. 4More work with Petrobras increases Brazilian firm's backlog to over $2 billion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free