Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›USACE Confirms Plans to Dredge Plymouth Harbor
Dredging

June 20, 2018 · about 8 years ago

USACE Confirms Plans to Dredge Plymouth Harbor

The U.S. Army Corps of Engineers, New England District, has just confirmed its plans to perform maintenance dredging of the Plymouth Harbor Federal navigation project in Plymouth, Mass. “Natural shoaling processes have reduced available depths to as little as 7.0 feet in the 18-foot main channel, 7.

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, New England District, has just confirmed its plans to perform maintenance dredging of the Plymouth Harbor Federal navigation project in Plymouth, Mass.

“ Natural shoaling processes have reduced available depths to as little as 7.0 feet in the 18-foot main channel, 7.0 feet in the 15-foot channel, and 4.0 feet in the 8-foot anchorage, making navigation hazardous at lower stages of the tide ,” said Project Manager Michael Walsh, of the Corps’ New England District , Programs/Project Management Division in Concord, Mass. “ Maintenance dredging of approximately 385,000 cubic yards of sand and silt from approximately 75 acres of the authorized project area will restore the project to authorized dimensions .”

According to the Corps, the 18-foot mean lower low water (MLLW) entrance channel contains approximately 41,000 cubic yards of fine sand. This material is proposed for placement at the Green Harbor Beach nearshore site dependent upon site capacity. The remaining material (approximately 344,000 cubic yards) is primarily silt and clay and proposed for placement at the Cape Cod Bay and Massachusetts Bay Disposal sites.

Construction is expected to take between 5-6 months within the allowable dredge window of Oct. 1 to Jan. 31 of any given year. The work is currently anticipated to be performed in 2018/2019 or 2019/2020.

USACE also added that if dredging is not completed in one season, construction will occur the following season within the allowable dredge window. The application of this window will limit adverse impacts to federally-listed endangered species and threatened species as well as avoid the eelgrass growing season, anadromous fish migrations, and the spawning of winter flounder and shellfish.

Proposed work is being coordinated with: U.S. Environmental Protection Agency; U.S. Fish and Wildlife Service; National Marine Fisheries Service; Massachusetts Office of Coastal Zone Management; Massachusetts Department of Environmental Protection; Massachusetts Division of Marine Fisheries; Massachusetts Historical Commission; Massachusetts Board of Underwater Archaeological Resources; Mashpee Wampanoag Tribe; Wampanoag Tribe of Gay Head (Aquinnah); Plymouth harbormaster and town Division of Marine and Environmental Affairs.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free