Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›Jumbo Sets Up Moheshkhali FSRU Mooring System
Subsea

May 4, 2018 · about 8 years ago

Jumbo Sets Up Moheshkhali FSRU Mooring System

Heavy lift shipping and offshore transportation & installation contractor Jumbo has completed work on the first LNG import terminal in Bangladesh. In 2017 Jumbo was awarded a contract by Geocean for the Moheshkhali Project. The Moheshkhali floating liquefied natural gas import terminal is being deve

1 minutes read
  • LinkedIn
  • X
  • Email

Heavy lift shipping and offshore transportation & installation contractor Jumbo has completed work on the first LNG import terminal in Bangladesh.

In 2017 Jumbo was awarded a contract by Geocean for the Moheshkhali Project. The Moheshkhali floating liquefied natural gas import terminal is being developed offshore Moheshkhali Island in the Bay of Bengal, Bangladesh.

The Moheshkhali floating LNG import terminal will include a floating storage and regasification unit (FSRU), a subsea buoy system and a subsea pipeline, which will connect the terminal to an onshore pipeline system.

Jumbo’s job was to transport and install the mooring system for the FSRU. This involved installing 8 suction piles/anchors, 1 pipeline end manifold (PLEM) and 1 Pad as well as scouring protection.

Mobilization began in mid-December 2017 with the installation execution going ahead in early January 2018. Works on the project have now been completed by the Jumbo offshore team and crew aboard the Jumbo Javelin.

Tom Rijnders , project manager at Jumbo said: “Conditions on this project were at times challenging due to strong currents and poor visibility, however, the crew on board managed to perform outstandingly with a lot of ingenuity and persistence to complete the project within specifications.”

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceEquipmentOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem wins multimillion-dollar rig jobs with Eni in Mediterranean and West Africa
  2. 2Woodside passes the baton for offshore gas project to Timor Gap in $200 million deal
  3. 3Fugro wins UXO survey contract for German offshore grid connections
  4. 4Accelerating operational excellence in offshore energy

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free