Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Tidal & Wave Energy›Seatricity moorings set for summer decommissioning
Tidal & Wave Energy

April 25, 2018 · about 8 years ago

Seatricity moorings set for summer decommissioning

Wave energy developer Seatricity has set a timetable to remove all residual mooring equipment used for Oceanus 2 wave energy device testing at Wave Hub.

2 minutes read
  • LinkedIn
  • X
  • Email

Wave energy developer Seatricity has set a timetable to remove all residual mooring equipment used for Oceanus 2 wave energy device testing at Wave Hub.

The decommissioning operation is expected to last up to ten days to remove five clump weights and lower elements of the mooring lines from the seabed, as that is the only infrastructure left in relation to Oceanus 2 deployment.

The moorings, consisting of five gravity anchors made of a single main reactive clump and four smaller clumps, were installed on May 31, 2014.

The first Oceanus 2 installation followed less than a month later. After series of trials, the Oceanus 2 device was recovered to Falmouth on August 20, 2016, and was not deployed since.

Whilst all efforts will be made to avoid diving, a dive team will also be on stand-by to support if required, according to Seatricity.

To remind, Devon-based marine contractor Keynvor MorLift (KML) was hired last year to perform the decommissioning.

KML will use the Severn Sea survey vessel, and Sarah Grey multicat vessel, to perform the retrieval with the assistance of the Ocean Enterprise support catamaran workboat.

As reported earlier, Seatricity planned to continue the trials on the Oceanus 2 device in 2017, but due to delays with the European Regional Development Fund (ERDF) grant funding, and the infrastructure decommissioning deadline, the testing of Oceanus 2 device at Wave Hub was discontinued .

Wave Hub is a grid-connected site for testing wave energy converters located offshore Hayle on the north coast of Cornwall, at the eastern edge of the Atlantic Ocean.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Tidal & Wave EnergyBusiness & FinanceOperations & MaintenanceResearch & DevelopmentTechnologyVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free