Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Post-Storm Analysis of the South Carolina Projects
Dredging

September 15, 2017 · about 9 years ago

Post-Storm Analysis of the South Carolina Projects

The U.S. Army Corps of Engineers, Charleston District, is currently conducting post-storm analyses on their federal storm damage reduction projects. The two federal storm damage reduction projects managed by the Charleston District in South Carolina are Folly Beach and the Grand Strand. “The Charles

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Charleston District, is currently conducting post-storm analyses on their federal storm damage reduction projects.

The two federal storm damage reduction projects managed by the Charleston District in South Carolina are Folly Beach and the Grand Strand.

“ The Charleston District will perform an initial assessment of Folly Beach this week and the Grand Strand early next week to document any sand loss from the projects ,” reported the Corps.

Once that is completed, a detailed report will be written and sent to U.S. Army Corps of Engineers Headquarters where it will be reviewed to see if the projects meet the necessary criteria to qualify for emergency funding.

Myrtle Beach Renourishment Update

The Myrtle Beach Storm Damage Reduction Project will resume construction at Surfside Beach in the coming days. The contractor, Great Lakes Dredge and Dock, will start pumping and dredging at 8th Avenue South and will move south, as originally scheduled.

USACE added that since weather and mechanical delays are built into the construction timeline, there will be no impact to the schedule. Construction on Garden City and Surfside Beach will be completed by the end of September and begin on North Myrtle Beach in October.

“ The portion of the project that was completed pre-Hurricane Irma successfully did the job it was intended to do ,” said Wes Wilson, project manager . “ The people and property behind the dunes were protected from major damage. If erosion did occur during Hurricane Irma, sand replacement would depend on funding and contractor availability.”

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Minesto enters MoU in Maldives for tidal energy development
  2. 2Samsung Heavy Industries unveils Canada-tailored FLNG solution
  3. 3Seatrium rakes in millions with Keppel’s RigCo to revive four stranded rigs
  4. 4Rig incident: 110 rescued, 5 still missing after Borr Drilling’s jack-up sinks off Gabon coast

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free