Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Absecon Island Beach Replenishment Starts in April
Dredging

March 20, 2017 · about 9 years ago

Absecon Island Beach Replenishment Starts in April

New Jersey’s last major Post-Sandy recovery project, the Absecon Island scheme is set to begin this April, according to the Department of Environmental Protection Commissioner Bob Martin. The $63 million beach fill project will be carried out jointly by the Cranford-based Weeks Marine company, the U

1 minutes read
  • LinkedIn
  • X
  • Email

New Jersey’s last major Post-Sandy recovery project, the Absecon Island scheme is set to begin this April, according to the Department of Environmental Protection Commissioner Bob Martin.

The $63 million beach fill project will be carried out jointly by the Cranford-based Weeks Marine company, the U.S. Army Corps of Engineers and DEP.

The Absecon Island project covers 8.1 miles of shoreline in Atlantic City, Longport, Margate and Ventnor.

DEP reported that the Ventnor and Atlantic City portions entail replenishment of beaches already designed to the Corps’ standards. The Longport and Margate sections involve new construction to bring beaches to USACE standards.

Beaches 200 feet wide will be constructed and dunes will be restored to an elevation of approximately 15 feet above mean sea level in Atlantic City. Longport, Margate and Ventnor will get 100-foot-wide beaches and dunes that are nearly 13 feet above mean sea level.

Atlantic City will see fill placed from Oriental Avenue to Jackson Avenue, as well as five outfall extensions or repair. The plan also calls for 0.3 miles of seawall and bulkhead construction along the Absecon Inlet frontage of Atlantic City.

The tentative schedule for the $63.3 million Absecon Island project is as follows:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1
  2. 2
  3. 3
  4. 4

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free