Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Prock Marine Wins Sagamore Creek Dredging Deal
Dredging

December 2, 2016 · about 10 years ago

Prock Marine Wins Sagamore Creek Dredging Deal

A portion of the Congressionally-authorized Back Channels portion of the Portsmouth Harbor and Piscataqua River Federal navigation project known as “Sagamore Creek” in Portsmouth and Rye, New Hampshire, will undergo maintenance dredging under the terms of a $542,970.00 contract issued recently by th

1 minutes read
  • LinkedIn
  • X
  • Email

A portion of the Congressionally-authorized Back Channels portion of the Portsmouth Harbor and Piscataqua River Federal navigation project known as “Sagamore Creek” in Portsmouth and Rye, New Hampshire, will undergo maintenance dredging under the terms of a $542,970.00 contract issued recently by the USACE’s, New England District.

Work will be accomplished by Prock Marine Company of Rockland, Maine.

The dredging operations are scheduled to start on or about January 10, 2017 and take about 4 to 6 weeks to complete. The contract was awarded on November 18, 2016.

“Approximately 4,300 cubic yards of predominantly sandy sediment will be dredged from the confluence of the three 6-foot navigation channels by mechanical dredge,” said Project Manager Mike Walsh, of the Corps’ New England District, Programs and Project Management Division in Concord, Mass.

“The sandy dredge material will be transported by scow and disposed of at a nearshore placement site adjacent to Wallis Sands Beach.”

The dredging is needed to restore that portion of the navigation project to authorized dimensions and alleviate shoal conditions that are impacting safe navigation. The work is scheduled to be completed before March 1 to minimize impact to natural resources in the area.

The project will be managed by the Corps under the supervision of a Corps’ Quality Assurance Representative to assure compliance with contract requirements.

[mappress mapid=”23323″]

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1
  2. 2
  3. 3
  4. 4

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free