Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›Panoro and Partners Make FID to Develop Aje Field, Nigeria
Subsea

October 8, 2014 · about 12 years ago

Panoro and Partners Make FID to Develop Aje Field, Nigeria

Panoro Energy ASA, together with the Joint Venture (“JV”) partners, has taken a Final Investment Decision (“FID”) to develop the Aje Cenomanian oil reservoir in the OML 113 licence in Nigeria. The Aje Field Development Plan (“FDP”) was submitted to Department of Petroleum Resources (“DPR”) earlier t

3 minutes read
  • LinkedIn
  • X
  • Email

Panoro Energy ASA, together with the Joint Venture (“JV”) partners, has taken a Final Investment Decision (“FID”) to develop the Aje Cenomanian oil reservoir in the OML 113 licence in Nigeria.

The Aje Field Development Plan (“FDP”) was submitted to Department of Petroleum Resources (“DPR”) earlier this year, and approval to develop Aje as proposed in the FDP was granted in March 2014.

The FDP is primarily focused on the development of the Cenomanian Oil reservoir and the first phase of the Cenomanian development (“Phase 1”) includes two subsea production wells tied back to a leased Floating Production Storage and Offloading vessel (“FPSO”). A contract for the charter of Rubicon’s Front Puffin FPSO has been signed, and modifications are scheduled to start shortly to bring her into specification for production on the Aje field.

Procurement of subsea equipment and the contracting of a drilling rig for the Phase 1 development is also ongoing. As part of Phase 1, the existing Aje-4 well will be re-entered and completed and a new well Aje-5, will be drilled.

The Aje-5 well will be drilled from a seabed location adjacent to Aje-4 and both wells will be connected via a subsea manifold and production flowlines to the FPSO. The Aje-5 well trajectory is designed to intersect the Cenomanian reservoir close to where the Aje-2 well intersected the Cenomanian reservoir.

Phase 1 has an estimated funding requirement of $220 million on a 100% field basis to reach first oil (total funding requirement net to Panoro is approximately $36 million). Panoro’s share of Phase 1 costs are expected to be funded through the Company’s available cash resources. The Company also has the financial flexibility to source an optimum level of debt for project development.

In July 2014 an independent review of the project was carried out by AGR TRACS International Ltd (AGR TRACS). AGR TRACS also assesses there to be additional contingent resources within the Cenomanian reservoir that may be accessed through a second phase of the development (“Phase 2”) comprising two further development wells in the Cenomanian Oil reservoir.

The JV partners envisage moving forward with Phase 2 once Phase 1 is on production, meaning that Phase 2 capital expenditure may be funded from Phase 1 production cash flow. Furthermore the separate Turonian gas reservoir which is rich in condensate and LPG and which also has a thin oil rim, has been assessed by AGR TRACS to contain significant additional contingent resources.

The JV partners will take a decision to proceed with a development of the Turonian reservoir at a later date. The Aje Field Cenomanian development decision is a very important milestone for the OML 113 JV partners in the commercialisation of all the discovered hydrocarbon resources on the licence.

First oil from Aje is scheduled for the end of Q4 2015 at an initial gross production rate of around 10,000 bopd based on AGR TRACS estimates. In conjunction with the ongoing development work, exploration activities on OML 113 continue with the processing of the newly acquired 3D seismic data.

The final Pre-Stack Depth Migration is scheduled for completion by end of Q1 2015. It is expected that the new survey will provide a considerable improvement in data quality over the existing 3D data.

It is envisaged that the data will enable better development planning for the Phase 2 of development drilling on Aje and provide improved data to fully evaluate the exploration potential over the whole of the OML 113 licence, including the exciting synrift exploration play that was significantly de-risked though the discovery made in the neighbouring OPL 310.

[mappress] Press Release, October 08, 2014

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceOperations & MaintenanceResearch & Development

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1AI solutions to track wildlife at Welsh 30 MW tidal energy project
  2. 2Rig sinking incident: Search continues for five missing as 'robust' probe looms
  3. 3Minesto enters MoU in Maldives for tidal energy development
  4. 4Samsung Heavy Industries unveils Canada-tailored FLNG solution

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free