Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Dana installs pipeline for Western Isles Project
Fossil Energy

May 20, 2014 · about 12 years ago

Dana installs pipeline for Western Isles Project

Dana Petroleum’s gas export-import pipeline for the Western Isles Development Project has been successfully installed onto the seabed.

2 minutes read
  • LinkedIn
  • X
  • Email

Dana Petroleum’s gas export-import pipeline for the Western Isles Development Project has been successfully installed onto the seabed.

The pipeline will export excess produced gas to the Tern – North Cormorant gas pipeline and import gas for lift gas and fuel when required.

The 11 kilometre long, six inch pipeline was fabricated and inspected at Subsea 7’s spoolbase in Leith and installed using the Seven Navica vessel. It is the first pipeline to be installed from the recently refurbished facility.

Hugh McClure , director of capital development projects, said: “We are pleased to have completed the first part of the 2014 offshore subsea campaign safely, successfully and on schedule. This is another important milestone achievement for the Western Isles Development Project.”

The Western Isles Project (Dana 77% and CIECO 23%) will develop two oil fields called Harris and Barra in the Northern North Sea, 160km east of the Shetlands and 12km west of Tern field. It involves a subsea development of at least five production and four water injection wells tied back to a new build floating production, storage and offloading vessel (FPSO) with oil export using shuttle tankers.

Following the FPSO keel laying ceremony in May 2013, top hole drilling began on the North Drill Centre in August 2013 and was completed within 67 days using the Ocean Nomad semisubmersible rig, leased from Diamond Offshore. A total of four subsea trees has now been successfully installed on the seabed. The gas export pipeline was installed in May 2014 with FPSO installation at a later date.

[mappress]

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & FinanceEquipmentProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Woodside passes the baton for offshore gas project to Timor Gap in $200 million deal
  2. 2Fugro wins UXO survey contract for German offshore grid connections
  3. 3Accelerating operational excellence in offshore energy
  4. 4Go-ahead for North Sea wildcat clears path for Equinor’s drilling ops with COSL rig

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free