Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›First oil flows at Dana Petroleum’s Western Isles Project
Fossil Energy

May 1, 2014 · about 12 years ago

First oil flows at Dana Petroleum’s Western Isles Project

Dana Petroleum has reported that the first production well has now been successfully completed and flow tested and a further three wells have been drilled and cased to surface casing depth in the Western Isles Development Project. All four subsea christmas trees have also been installed on the seabe

1 minutes read
  • LinkedIn
  • X
  • Email

Dana Petroleum has reported that the first production well has now been successfully completed and flow tested and a further three wells have been drilled and cased to surface casing depth in the Western Isles Development Project.

All four subsea christmas trees have also been installed on the seabed. The work is being undertaken by the drilling rig Ocean Nomad which has been leased from Diamond Offshore.

Hugh McClure , director of capital development projects, said: “ The first flow on Western Isles is an important milestone for both the project and Dana as a company.”

The Western Isles Development Project (Dana 77% and CIECO 23%) will develop two oil fields called Harris and Barra in the Northern North Sea, 160km east of the Shetlands and 12km west of Tern field. It involves a subsea development of at least five production and four water injection wells tied back to a new build floating production, storage and offloading vessel with oil export using shuttle tankers.

Following the FPSO keel laying ceremony in May 2013, top hole drilling began on the North Drill Centre in August 2013 and was completed within 67 days using the Ocean Nomad semi-submersible rig, leased from Diamond Offshore. A total of four subsea trees have now been successfully installed on the seabed. The gas export pipeline will be installed in summer 2014 and FPSO installation at a later date.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Dolphin Drilling parts ways with 52-year-old rig and forges pact with SPM
  2. 2Fugro's 18-meter USV on survey duty at 'world's longest interconnector'
  3. 3Energy Drilling lines up 30-month job to keep its rig busy through 2030
  4. 4Siem Industries orders two subsea construction vessels from China

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free