Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Norway: PSA Conducts Audit on Working Enviroment Conditions on West Elara Jack-Up
Fossil Energy

July 20, 2011 · about 15 years ago

Norway: PSA Conducts Audit on Working Enviroment Conditions on West Elara Jack-Up

During the period 4-7 July 2011, the Petroleum Safety Authority Norway (PSA) conducted an audit of working environment conditions on the facility West Elara. Background The PSA’s activity was conducted as part of the processing of the company’s application for an Acknowledgement of Compliance (AoC).

1 minutes read
  • LinkedIn
  • X
  • Email

During the period 4-7 July 2011, the Petroleum Safety Authority Norway (PSA) conducted an audit of working environment conditions on the facility West Elara.

Background

The PSA’s activity was conducted as part of the processing of the company’s application for an Acknowledgement of Compliance (AoC). The facility will be used as a drilling facility for Statoil on the Norwegian continental shelf.

Objective

The objective of the audit activity was to verify that selected technical working environment-related factors on the facility were designed in accordance with applicable regulatory requirements.

Result

The main impression is that Seadrill has largely set up suitable processes to follow up safeguarding of the working environment-related factors in various areas on the facility.

The project’s verification activities have resulted in the identification of a significant number of nonconformities in relation to the regulations’ working environment requirements, mostly due to deficient follow-up.

A lot of work remains as regards correction of nonconformities. PSA did note good management and status as regards correcting identified deficiencies.

During the audit, new nonconformities were identified in connection with:

Furthermore, potential improvements were identified in relation to:

[mappress] Source: PTIL, July 20, 2011; Image: Seadrill;

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free